Title 15 Amendment Analysis for Spanish Fork
An independent, source-by-source review of proposed §15.3.24.090, data centers with onsite power generation in the I-1 zone, prepared ahead of the Spanish Fork City Council vote on 18 AUG 2026.
1. Executive summary
The choice is not this warehouse site versus an empty field, it is the proposed data center versus the distribution warehouse the building was originally built for. Against that alternative, the proposed data center build is better on every measurable dimension for the city.
No drawback to the community was found in the facility as proposed and as permitted. Sound and heat are the only effects that travel, and the nearest existing home is 1,298 ft away.53 Against that alternative, truck traffic goes from thousands of diesel trips a month to none, water use drops, there is no diesel on site, and the municipal grid carries none of it. §6 sets out the alternative use side by side, §10 the air permit, §20 sound and heat.
The tax base benefits the whole community, not just the city. Roughly 90% of the levy goes to entities serving these same residents: Nebo School District takes 75.2%, about $30.1M in year one against the city's own $4.0M.1559 Volition has separately committed to more than $500,000 a year in direct community contributions, itself 15× the city's property tax take from its largest commercial taxpayer.5773 §13 carries the arithmetic, the depreciation curve, and the caveat that no development agreement is signed yet, though Volition has so far accepted every substantive suggestion from the community and from staff.
The performance standards do their job. §6 caps noise at 65 dBA at any property line and 55 dBA at any residential zone boundary, at any hour, covering generation, storage and cooling equipment, measured under Chapter 9.32 and without displacing Chapter 9.32 enforcement.51 Evaporative cooling is banned outright, diesel is excluded by definition, and the permitted emission rates are a zoning condition the city can enforce. §8 and §20 carry the detail.
One question is worth putting to the Council on Tuesday, and it is a point of clarification: The amendment binds every applicant in the I-1 zone at up to 500 MW per facility.151 Its redline struck "approved as a conditional use" and "conditionally permitted" from every operative clause, while leaving the use heading pointing at "(see §15.3.08.060)", the Conditional Use Permit chapter that carries a public hearing and five findings.51 So the enacting text reads as administrative site plan review, and one stray cross-reference is the only thing suggesting otherwise. §9 sets out the redline in full.
Does §15.3.24.090 route these facilities through site plan review, or through the Conditional Use Permit chapter that the use heading cites?
2. Scope and sourcing
The Volition proposal is treated as evidence of how the text performs against a well-documented project. Every quantity below is stated at the maximum the amendment itself permits: 500 MW per generation facility.11
This report prioritizes primary sources across official municipal, city, county, state, and federal records, plus an adversarial red team review of each claim and individual verification of every cited source. The binding ordinance text comes from the 18 AUG Council packet with page-level citations and color-verified redlines.51 The city's official 04 AUG City Council meeting, 05 AUG Planning Commission meeting, and the 15 AUG Volition community meeting supply the record. The applicant's own materials from that meeting, its printed two-sided handout61 and the live project page its QR code resolves to,4 are treated as primary sources and audited in full. Parcel, tax, and receptor geometry come from the Utah County Assessor and Recorder and from computation against the state's parcel polygons. Field research was carried out directly: on-site visits to comparable operating facilities, in-person interviews with residents, employees, and neighboring businesses, and uncalibrated sound level readings, all reported below with their limits stated.
Everything material here is fully sourced unless otherwise marked. Where a claim could not be confirmed against a primary document it is marked UNVERIFIED. Where a physical observation was taken without professionally-calibrated instruments it is marked UNCALIBRATED and treated as corroboration only. Where the applicant has committed to something on the record but no signed instrument exists it is marked COMMITTED, NOT EXECUTED: the commitment is taken as made in good faith, and nothing is final until a written agreement signed and dated by both the City and Volition exists.
3. Bottom line
Volition describes a 250 MW compute load; the air permit it has applied for would authorize 393.25 MW of nameplate, 1,210 fuel cells at 325 kW each.13 The ordinance would authorize 500 MW per generation facility, and its two-site quota expressly does not apply to standalone generation facilities.1151
The real risk is that this zoning decision is the only discretionary review any facility built under this text will ever receive. Utah's 2025 S.B. 132 created a "closed private generation system" category describing this project exactly and exempting it from Public Service Commission regulation; no interconnection means no utility review.12 DAQ's minor-source order is ministerial and weighs no siting question. Spanish Fork land use is the last stop in the system for oversight of any kind. Which makes one drafting question worth putting on the record Tuesday: the amendment's redline struck conditional-use status from every operative clause but left the use heading citing the Conditional Use Permit chapter, so the text reads as administrative site plan review with one stray cross-reference against it. §9 sets out the redline.
4. What the amendment authorizes, at its own maximum
§15.3.24.090 permits "not more than 500 megawatts of nameplate generating capacity, measured per Onsite Power Generation Facility," and no less than 50.51 500 MW is the number the Council is actually voting on, and it is 27% larger than the 393.25 MW Volition has applied for.151
The figures below use Utah DAQ's own method. DAQE-IN163550001-26 derives every permitted limit as the manufacturer's published rate times full nameplate times 8,760 hours.43 Applying that arithmetic at the ordinance's own cap is not a hypothetical worst case; it is the state's method at the city's number.
The maximum the amendment authorizes is stated first, because that is what the Council is voting on. The expected case, Volition's permitted 393.25 MW, follows in the last column. Neither number is a prediction.
TABLE 01
| MAXIMUM: one facility at the 500 MW cap | MAXIMUM: two sites, citywide | Expected: Volition as permitted, 393.25 MW 111 | |
|---|---|---|---|
| Bloom ES 6.5 units | 1,538 | 3,076 | 1,210 43 |
| CO2 equivalent | 1,825,029 TPY | 3,650,057 TPY | 1,434,855 TPY 143 |
| Nitrogen oxides | 6.57 TPY | 13.14 TPY | 5.17 TPY 143 |
| Carbon monoxide | 28.47 TPY | 56.94 TPY | 22.39 TPY 143 |
| Volatile organic compounds | 21.90 TPY | 43.80 TPY | 17.22 TPY 143 |
| Heat rejected | 769–943 MW-thermal | 1,538–1,887 MW-thermal | 605–742 MW-thermal 43 |
| vs Lake Side Power Plant | 58–72% | 117–143% | 46–56% 43 |
| Natural gas | 24.5–30.1 Bcf/yr | 49–60 Bcf/yr | 19–24 Bcf/yr 43 |
| Water, annual | ~318,000 gal | ~636,000 gal | 250,000 gal 434451 |
| Fuel cell yard | 14–18 acres | 28–36 acres | 11–14 acres 43 |
| Against the city's ~90 MW peak | 5.6× | 11.1× | 4.4× 4351 |
| Against UMPA's FY2027 forecast peak, 115.76 MW | 4.3× | 8.6× | 3.4× 5 |
Two sites at the cap would reject more heat than Lake Side Power Plant, the 1,315 MW-thermal gas plant in Vineyard, and would burn 49 to 60 billion cubic feet of natural gas a year.33
The two-site quota caps data center self-generation power levels
§13, verbatim:
"Not more than two Data Center with Onsite Power Generation Facility sites… shall be approved and active within the corporate limits of Spanish Fork City at any time… This limitation does not apply to a standalone Onsite Power Generation Facility established without an associated Data Center."
The citywide ceiling is therefore not 1,000 MW. It is 1,000 MW of data-center-paired generation plus an uncapped number of standalone Onsite Power Generation Facilities, each permitted up to 500 MW.11 This is just a noted observation for future consideration.
Where this could go, and where it could not
Any parcel in the I-1 Light Industrial zone qualifies. The amendment is citywide in application, not site-specific: the applicant requested a text amendment, not a rezone of one parcel. The next applicant need not be Volition, need not use Volition's equipment, and need not carry any of the six covenants Volition volunteered. It needs only to meet the objective conditions in §15.3.24, and it is approved administratively.11
How far that opens is itself a drafting question. The qualifying test is a performance standard, not a technology: equipment must be CARB-certified or emit NOx at no more than 0.5 lb/MWh, and reciprocating internal combustion engines are excluded outright.51 Fuel cells are named as equipment that meets the standard rather than required by it. But the redline struck the words "without limitation" from that list, and struck "recuperated microturbines" out of it, which is the standard way an open list becomes a closed one.
What the ordinance does constrain: generation must be Ultra-Low Emission Technology, permanently islanded, non-evaporatively cooled, held to 65 dBA at the property line and 55 dBA at any residential boundary at all hours, water-capped by permit condition, and subject to battery fire-safety review.11 No other Utah jurisdiction examined imposes any of those.
5. The local yardstick
what 500 MW looks like against everything already here
Every figure here comes from Utah DAQ's reported emissions inventory: 256 facility-year records covering 71 permitted Utah County facilities, 2017 through 2025.9 These are reported actual numbers.
Every permitted air source inside Spanish Fork
There are three. Grouping by DAQ facility ID rather than company name collapses two pairs that are the same plant under successive owners: DAQ_ID 10847, Sapa Extrusions and Hydro Extrusion USA, one facility whose street address moved from 1550 N Kirby Lane to 1550 Hydro Way after Norsk Hydro renamed the road; and DAQ_ID 11789, Longview Fibre and WestRock Longview, one facility at 2200 North Main Street with identical coordinates in every year.9
TABLE 02
| Facility | DAQ ID | Year | NOx tons/yr | CO | PM2.5 |
|---|---|---|---|---|---|
| Hydro Extrusion USA, LLC, 1550 Hydro Way | 10847 | 2025 | 17.89 | 16.88 | 2.85 9 |
| WestRock Longview, LLC, 2200 N Main St | 11789 | 2023 | 4.16 | 12.78 | 0.86 9 |
| Staker & Parson, Gomex Pit (the quarry southeast of the site) | 12130 | 2023 | 0.00 | 0.00 | 0.02 9 |
| Whole city, all permitted sources | 22.05 | 9 |
Hydro Extrusion is 81% of every permitted ton of NOx in Spanish Fork, and nothing else is close.43 35
Comparison of NOx
TABLE 03
| Facility | City | Year | NOx tons/yr | vs city total (22.05) |
|---|---|---|---|---|
| PacifiCorp, Lake Side Power Plant | Vineyard | 2025 | 176.42 9 | |
| UAMPS, Nebo Power Station | Payson | 2025 | 52.35 934 | |
| Spanish Fork's entire permitted industrial base | n/a | n/a | 22.05 9 | |
| Hydro Extrusion, the city's largest source | Spanish Fork | 2025 | 17.89 9 | 81% |
| Two data-center sites at the 500 MW cap | n/a | n/a | 13.14 1143 | 60% |
| One facility at the 500 MW cap | n/a | n/a | 6.57 1143 | 30% |
| Intermountain, Utah Valley Regional Medical Center | Provo | 2023 | 5.44 9 | |
| Volition as permitted, 393.25 MW | Spanish Fork | n/a | 5.17 1 | 23% |
A 393 MW data center is permitted for about the same annual NOx as the region's main hospital, a 395-bed facility. On NOx specifically this technology is clean, and the state's own inventory proves it. A facility at the full cap would rank below the aluminum plant Spanish Fork already hosts.411 Two sites at the cap would emit 73% of Hydro Extrusion's total and become the city's second-largest NOx source, four times WestRock.43 (Spanish Fork's own 33-bed hospital holds a DAQ Approval Order but reports no emissions yet, so Provo's 395-bed facility is the meaningful hospital comparator.)954
Everything Spanish Fork generates today is wind, solar, or water. It has never had a thermal power plant. Its neighbors have. UAMPS Nebo, 20 minutes down the road, already reports 8× the NOx a 500 MW facility would be permitted for, and PacifiCorp's Lake Side in Vineyard, 1,204 MW combined, reports 176 tons, 27× the 500 MW figure.113334 Lehi, Springville and Payson each run their own plants, at 7.39, 3.37 and 0.57 tons respectively in 2025.9
Every generator that already exists inside Spanish Fork
From the Utah Geological Survey electricity series, reproducing EIA Form EIA-860 filings. All capacities are AC, and EIA lists only solar and hydro units above 1 MW.
TABLE 04
| Plant | Type | Operator | Nameplate | Online |
|---|---|---|---|---|
| Spanish Fork Wind Park | Wind, nine turbines | NRG Energy Gas & Wind, now Clearway | 18.9 MW | Jul 2008 8 |
| Spanish Fork Community | Solar-PV | Utah Municipal Power Agency | 4.0 MW | Jul 2021 7 |
| Spanish Fork | Hydroelectric, three units | Strawberry Water Users Association | 3.6 MW | 1937 / 1983 6 |
| All generation inside Spanish Fork | 26.5 MW | 43 |
The wind park runs nine Suzlon S88 2.1 MW machines at a 33.52% capacity factor, selling under a PSC-approved power purchase agreement; it is the only utility-scale wind generation in Utah County.811 The solar park is UMPA's, sold to residents through the city's SharedSolar program and built on a closed landfill.72122 The hydro plant is on Powerhouse Road, and it is the reason the road has that name: three units under the Strawberry Water Users Association, the oldest in service since 1937.1055 Powerhouse Road serves the current warehouse site, and the city straightened it for this building's truck traffic.6112343
Only one of those three actually supplies Spanish Fork customers. The wind park sells to PacifiCorp under a 20-year PPA and the hydro plant to the South Utah Valley Electric Service District; only the 4.0 MW solar park serves the city.67821 Spanish Fork is not a Rocky Mountain Power city, it runs a municipal utility supplied wholesale by UMPA, whose largest resource is market purchases, 52% of all energy delivered.5
Filed nameplate against filed nameplate, with no assumptions: Volition as permitted is 14.8× all 26.5 MW of existing city generation, one facility at the 500 MW cap is 18.9×, and two sites at the cap are 37.7×.181143
Who actually uses the power, and what the amendment would add to it
UMPA files Spanish Fork's retail book by customer class (FY2022 Customer Profile, IRP p. xiii). This is the city's electrical demand:
TABLE 05
| Class | Accounts | kWh sold | Share |
|---|---|---|---|
| Residential | 12,450 | 118,985,545 | 40% 5 |
| Commercial | 1,728 | 121,460,898 | 40% 5 |
| Large Commercial | 5 | 48,019,200 | 16% 5 |
| Industrial | 1 | 386,000 | under 1% 5 |
| Agricultural | 10 | 1,663,784 | 1% 543 |
| Streetlights | 3 | 53,994 | under 1% 5 |
| Other | 271 | 8,307,952 | 3% 5 |
| Total | 14,468 | 298,877,373 | 5 |
UMPA does not name customers in thier paperwork, but the filing establishes the ceiling. Hydro Extrusion and Mountain Country Foods are both certainly inside the five-account Large Commercial class, which consumes 48.02 GWh a year in total, so even if one plant were that entire class it would use 48 GWh a year.528
TABLE 06
| Annual energy at 75% load | vs the city's 297.3 GWh | vs the whole Large Commercial class 5 | |
|---|---|---|---|
| Volition as permitted, 393.25 MW | 2,584 GWh | 8.7× | 53.8× 143 |
| One facility at the 500 MW cap | 3,285 GWh | 11.1× | 68.4× 1143 |
| Two data-center sites at the cap | 6,570 GWh | 22.1× | 136.8× 43 |
One facility built under this amendment would consume eleven times the annual electricity of every home, business, farm, and streetlight in Spanish Fork combined, roughly 68x the entire class its largest industrial neighbors sit in, and 19x every generator in the city. Two sites would be 22x the city.43 It also explains why the off-grid design is an engineering necessity rather than a marketing choice: there is no version of this facility that the city's distribution system could carry. The building's own leasing listing puts the point beyond argument: 4,000 A at 480 V with roughly 6 to 8 MW of additional power advertised as available, against a permitted 393.25 MW.55
City staff priced a grid-connected 50 MW load at "two new substations… 30 to 40 million dollars", which describes the municipal distribution system.51 Transmission capacity is a separate matter, and there is a great deal of it nearby. Federal HIFLD transmission mapping shows Spanish Fork is a 345 kV hub: four 345 kV circuits (Camp Williams, Emery, Huntington, Still Mill), two 138 kV circuits to Carbon, and roughly a dozen 115 kV lines owned by Spanish Fork City, PacifiCorp and Provo City all converge at the Spanish Fork substation, which sits about 1,530 m, 0.95 miles, almost due north of the parcel (bearing 9°).405343 So the honest statement is narrower than "the grid cannot serve this": the city's distribution system cannot, and transmission-level service would be an entirely different proceeding. Why that matters is the next section.
Additional context
NOx is the dimension where this technology wins, and it is the only one. None of these comparators carries anything close to the facility's CO2e, rejected heat, or gas throughput at the cap; Lake Side, the one Utah County facility at comparable thermal scale, would be exceeded by two sites at the cap.33
6. What is actually being proposed
Volition Industries, Inc. applied on 10 JUL 2026 for a Spanish Fork Title 15 text amendment permitting data centers with on-site generation in the I-1 Light Industrial zone. The target is the existing 1,054,000 sq ft former Fingerhut building at 4000 E US Highway 6, marketed since as Western Distribution Center and now as Canyon Logistics Center, at the mouth of Spanish Fork Canyon.5510
The warehouse data
TABLE 07
| As recorded5510 | |
|---|---|
| Total building | 1,054,000 sq ft, of which 46,944 sq ft is office |
| Currently on the market | Up to 451,792 sq ft, divisible to 196,249 sq ft, in two spaces |
| Loading | 36 dock-high doors plus one (1) 12'×14' grade-level door |
| Clear height | 36 ft |
| Column spacing | 45 ft × 46 ft |
| Fire protection | ESFR sprinkler |
| Year built | 1998 |
| Site | 69.478641 acres per the Assessor; the listing states 69.95 |
| Owner of record | WDC Industrial Utah Owner LP |
| 2026 market value | $50,898,400 |
| Electrical service | 4,000 A, 480 V, 3-phase, with approximately 6 to 8 MW of additional power available |
First, the vacancy. 451,792 of 1,054,000 sq ft, about 43% of the building, is being actively marketed, which is what "partly occupied" means in this report and is the closest thing to a measured baseline that exists.55
Second, the listing quantifies the grid constraint from the property's own side. The building is served at 4,000 A, 480 V, 3-phase, roughly 3.3 MVA, and its broker advertises 6 to 8 MW of additional power as available.55 Volition's permitted 393.25 MW is ~50 to 65 times that headroom, and the ordinance's 500 MW cap is 60 to 80 times it.11143
And the 36 dock doors are the truck-traffic argument. A building with 36 dock-high positions and one grade door was designed for continuous trailer cycling. The data center uses none of them.51
The alternative use, side by side
The counterfactual is this building operating as designed, not an empty field.
TABLE 08
| Distribution warehouse, the alternative use | Volition as permitted | |
|---|---|---|
| Truck traffic | 6,400 to 12,800 diesel truck trip ends a month, that is 3,200 to 6,400 truck visits, at full 24/7 occupancy by a large distribution tenant 414243 | None regularly. The facility has no loading or distribution operations. The honest figure is a few hundred local employee vehicle trips per day, all passenger cars 5143 |
| Water | Not established at full occupancy. No meter record for this building exists in the public record | 250,000 gal/yr, humidification make-up only, site irrigation not included. Evaporative and once-through cooling banned in the text itself (§9) 51 |
| Diesel engines on site | Every truck, every day | None. Reciprocating engines are excluded by definition 51 |
| Municipal grid draw | Standard industrial load | Zero. Permanent electrical isolation (§5) 51 |
| Permitted NOx | Not separately permitted | 5.17 tons/yr, against 51.28 at the nearest operating comparable 131 |
| Hazardous air pollutants | Not separately permitted | None permitted, against 31.6 tons/yr at that comparable 31 |
| Permanent jobs | Current employment at this building is not in the public record 43 | 100 to 200 permanent positions, and Volition told the Planning Commission it intends to headquarter in this building, which would put corporate roles here on top of operations 5175 |
| Taxable value | Existing $50.9M 10 | ~$4 billion claimed 51 |
Truck traffic
Every truck figure below is computed from published ITE rates applied to the verified 1,054,000 sq ft, using rate equations reproduced by two state transportation departments.414243 No traffic count for this building exists in any public record, so this describes a fully tenanted building, not present conditions of utilization, which are known to be very low.
ITE defines a high-cube warehouse as one with at least 200,000 sq ft and a ceiling height of 24 feet or more.42 This building is 1,054,000 sq ft with 36 ft clear height, so it is unambiguously high-cube, and Land Use Code 154 fits it better than the general Land Use Code 150 that warehouse traffic studies default to.
TABLE 09
| Method | Rate applied | Truck trip ends, weekday | Per month | Truck visits/month | Loads per door per day |
|---|---|---|---|---|---|
| ITE LU 150, general warehousing | 0.54 per 1,000 sq ft 42 | 569 | 12,849 | 6,424 | 7.9 |
| Observed share, sites ≥1,000,000 sq ft | 20% of 1,711 total trip ends 4142 | 342 | 7,725 | 3,862 | 4.8 |
| ITE LU 154, high-cube, the fitting code | 0.22 per 1,000 sq ft 42 | 232 | 6,396 | 3,198 | 3.2 |
Total weekday vehicle trip ends of 1,711 are the ITE LU 150 equation T = 1.58(X/1,000) + 45.54 at X = 1,054,000 sq ft.41 Monthly figures use 21.75 weekdays and 8.69 weekend days, with weekend volume scaled by each code's own published weekend-to-weekday ratio. ITE rates are trip ends, so one truck arriving and leaving is two trips.43
The dock doors provide an independent physical check, and it corroborates the lower half of the range. At 36 dock-high positions, the three methods imply 3.2, 4.8 and 7.9 trailer loads per door per day on a 24/7 operation. Three loads per door per day is ordinary; eight is a hard-running cross-dock. Working the check the other way, 36 doors at three loads per door per day gives 6,575 truck trip ends a month, which lands on the LU 154 figure almost exactly.43
The lower half is better supported, where the fitting land use code, the observed truck share for this size class, and the dock-door check all agree. The data center generates none of it, having no loading or distribution operations.51
TABLE 10
| Capacity | 250 MW delivered; applicant requested a 400–500 MW nameplate cap 1151 |
| Technology | Bloom Energy Server 6.5 solid-oxide fuel cells, natural gas, 325 kW per unit × 1,210 units, 393.25 MW combined nameplate, per the state air permit. 250 MW is the rack-level compute load 1351 |
| Grid | Zero interconnection, permanent electrical isolation, no export. Office/custodial may connect |
| Diesel | None, anywhere, including backup |
| Cooling | Closed-loop direct-to-chip liquid cooling, no evaporative towers, no plume (deck P-09). One fill of ~500,000 gal, intended to last the glycol service life of ~7–8 years. The separate ~250,000 gal/yr is humidification make-up, not loop refill. The ordinance independently bans evaporative and once-through cooling for any future applicant (§I9) 51 |
| Gas | Enbridge, new dedicated lateral, ~$14M at Volition's expense (unverified) 51 |
| Investment | ~$4B, building retrofit, fuel cells, electrical, fire, security, engineering. Stated identically in both decks. Note the itemization excludes compute hardware, which puts infrastructure at ~$16M/MW, a figure that does not reconcile cleanly with fuel cell costs and warrants a line-item capital stack 51 |
| Jobs | 400–600 construction (deck) / "over a thousand" (testimony); 100–200 permanent at $85–90k+ 51 |
| Tax | ~$40M/yr claimed 51 |
| Timeline | First ~25 MW ~AUG 2027; full buildout end of 2028, conditional on "a complete contract" 51 |
| Tenant | Nscale named in testimony; unconfirmed anywhere in Nscale's public record |
Scale in context: the whole city's peak electrical demand is roughly 90 MW. UMPA's Integrated Resource Plan, filed 30 NOV 2022, records Spanish Fork City's FY2021 annual peak at 74.10 MW against 297,313 MWh of annual sales for 14,468 customers, and forecasts that peak growing to 115.76 MW by FY2027 (IRP pp. 81 to 82).5 The ~90 MW figure used in the city record on 04 AUG sits between the two, so this report uses it as the current-era number and shows the FY2027 forecast alongside.51 Every scale multiple below survives either figure. At 250 MW the facility generates ~2.8× the whole city's peak consumption; at the 500 MW cap, ~5.6×, or 4.3× against the FY2027 forecast.1151 It also explains why the off-grid design answers a real constraint rather than a marketing one: city staff put a grid-connected 50 MW load at "two new substations… 30 to 40 million dollars," and a 250 MW grid-tied load in Spanish Fork is not possible at all.51
7. Where the procedural record actually stands
TABLE 11
| Date | Event |
|---|---|
| 29 JUL 2026 | Development Review Committee recommends approval |
| 04 AUG 2026 | Council discussion item. No vote |
| 05 AUG 2026 | Planning Commission public hearing. Motion to recommend approval FAILED 3–3. A separate motion reportedly passed 5–1 adding a power cap, a facility quota, and a heat study 28 |
| 18 AUG 2026 | Council public hearing, item 7.3. Posted. No continuance 2028 |
The Planning Commission did not endorse this. It deadlocked. Text-amendment review is advisory, so it advances regardless.
Two councilmembers asked for exactly this discretion on 04 AUG
The city's own approved-form minutes (packet pp. 59–71) record this exchange during the large-load work session, before the Volition presentation:51
"expressed concern that a business could potentially be a permitted use within a zone while still requiring an exceptionally large amount of electricity. In that circumstance, the Council might have no legislative opportunity to evaluate the broader impacts… He suggested that users exceeding certain thresholds might warrant a process similar to a conditional use review." (p. 61) A second councilmember "agreed that the concern would likely require changes to Title 15… under the existing code, those businesses would not necessarily require Council review." (p. 61) The city manager "explained that the draft large-load policy itself might not provide the legislative authority [the councilmember] had been seeking and said staff could further examine what type of legislative action might be appropriate." (p. 62)
The amendment reaching the Council on 18 AUG does not contain that review, and nothing in the public record shows that examination happening. Two councilmembers and the Planning Commission have now asked for discretion the ordinance does not contain, and no one in the public record argued for removing it. Staff's rationale, that pre-set objective standards are more legally defensible than ad hoc discretionary ones, is mainstream and legitimate, but it was never weighed against those asks in any document available to the public.
8. The ordinance, provision by provision
Source: https://www.utah.gov/pmn/files/1467389.pdf, pp. 61–66.
Genuinely strong:
- "Ultra-Low Emission Generation Technology", CARB-certified or NOx ≤ 0.5 lb/MWh; explicitly "does not include reciprocating internal combustion engines." Objective, numeric, verifiable, and it categorically excludes the gas engines Novva and Joule Capital actually built.11 Bloom's ES 6.5 datasheet states 0.003 lb/MWh of NOx, a 167× margin.3 (0.07 lb/MWh is the CARB DG certification standard, the ceiling a unit must beat to be certified, not Bloom's rate.)30
- §F6 Noise is the strongest performance standard in the document. Verbatim: sound "including generation equipment, Energy Storage Systems, and cooling equipment, shall not exceed 65 dBA at any property line of the site, and shall not exceed 55 dBA at the boundary of any residential zone, at any hour, measured in accordance with the procedures of Chapter 9.32 of this Code," and "compliance with this subsection does not excuse compliance with Chapter 9.32."51 So it is a continuing limit, not a design target; it names cooling equipment, the source that generates complaints nationally; it adopts a measurement procedure; and it preserves the city's standing enforcement. Against the existing I-1 limit of 80 dBA day / 65 dBA night, a facility here must meet the city's nighttime standard around the clock. Volition wrote this. The one omission is a scheduled test after construction, leaving enforcement to complaint under Chapter 9.32.
- §I9, closed-loop, air-cooled, or dry cooling required; evaporative and once-through banned. This converts the water promise into law and is the most valuable protection in the document.
- §E5, permanent electrical isolation, no interconnection, parallel operation, or export.
- §9 Water Use was strengthened: applications must include "an annual water use estimate, by category of use", explicitly covering landscaping, reviewed by the Public Works Director, and "the approved estimate shall be a condition of the permit." This closes the landscaping gap that went unregulated at Novva.
- §7 Air Quality requires the facility to "at all times operate within the emission rates demonstrated under subsection C", making the emission rates a zoning condition the city can enforce, not merely a DAQ matter.
- §4 Energy Storage requires UL 9540 listing, UL 9540A large-scale fire test data, NFPA 855 compliance, and Fire Marshal review with an emergency response plan before certificate of occupancy.
The enacting Exhibit A and the item 7.3 staff memo come from the 18 AUG Council packet, retrieved from the Diligent portal.2051 Full detail in FINDINGS-18AUG-ORDINANCE.md; the binding text is sources/18AUG-council-agenda-packet.pdf.
The text carries a capacity ceiling, and it is the number to argue about. §2 reads "…a minimum of 50 megawatts and not more than 500 megawatts of nameplate generating capacity, measured per Onsite Power Generation Facility."51 Note the floor as well as the ceiling: nothing under 50 MW qualifies at all, so every facility this text authorizes is a large one. The section above works through what that permits at the cap.
Still materially weak in the text going to a vote:
- No heat or thermal standard of any kind. The Commission's third recommendation, a deeper discussion of heat impacts, did not make it into the ordinance. At 605–742 MW-thermal this remains the clearest substantive gap, and the Commission itself asked for it.43
- §K11 decommissioning: unchanged. Exhibit A still reads "The City may require a decommissioning plan" within 12 months. No bond, no surety, no escrow.51
- §J.10, sewer discharge is NOT prohibited, only subject to pretreatment. Staff confirmed this on the record. The Volition representative testified "there is no scenario where we are offloading water." The ordinance and the testimony cannot both be the operative commitment.
- No GHG provision, and no regulator in this process will supply one. Utah DAQ quantifies CO2e in approval orders but does not cap it, and GHG BACT does not reach minor sources.
- The by-right mechanism, the one item on this list worth a question on Tuesday. Exhibit A contains zero occurrences of "Conditional Use Permit", "conditional use" or "Planning Commission may impose", against three of "site plan application", and the applicant's own §L discretionary-conditions clause does not exist in the enacting instrument.51 The redline shows the removal was deliberate, striking conditional-use language from four separate clauses while leaving the heading's "(see §15.3.08.060)" cross-reference in place. §9 sets that out in full, and it is the single clarification this report recommends asking for.
Of the six volunteered covenants, five are substantially in the text: no grid interconnection (§5), the noise limit (§6), no diesel engines (via the Ultra-Low Emission definition), decommissioning (§11, but without financial assurance), and the water use cap, which §9 makes a binding permit condition. Only annual public reporting is missing. No draft development agreement is publicly posted anywhere.
9. The best question on the agenda
Exhibit A still points to the hearing chapter
This is the strongest finding in the review, and no keyword search will surface it. It was found by following a cross-reference rather than searching for a phrase.
What Exhibit A contains, and what it does not
Exhibit A is §15.3.24.090, subsection O, items 1 through 13. Read in full, two things are true at once.51
TABLE 12
| In Exhibit A | Status |
|---|---|
| "B. Uses Subject to Conditions (see §15.3.08.060)" | Present, in the I-1 use heading |
| Any use of the phrase "conditional use permit" | Absent |
| Any grant of authority to the Planning Commission to impose conditions | Absent |
| "site plan application" as the operating procedure, at items 3, 6 and 9 | Present |
| §7's cross-reference to "the emission rates demonstrated under subsection C" | Present, and dangling. Exhibit A has no subsection C; it is numbered 1 through 13 |
| §13's cross-reference to "§15.3.16.120(C)" | Present, and dangling. Exhibit A renumbers that heading to B |
So the enacting text routes these facilities through site plan review, contains no Planning Commission conditioning authority anywhere, and still carries a heading that points at the Conditional Use Permit chapter, where the public hearing and the five mandatory findings live.11 Whether that cross-reference imports those procedures or is inert decides whether any facility built under this text ever gets a hearing.
The packet contains two documents that describe different ordinances
The justification statement travels in the same packet the Council votes from, and on four points it does not describe Exhibit A:51
TABLE 13
| The justification statement says | Exhibit A says |
|---|---|
| "Every project under this text still needs its own conditional use permit, its own public hearing, and its own site-specific conditions." | Neither phrase appears. Site plan review. |
| "The Planning Commission keeps full conditional use authority to impose site-specific conditions on each project." | No such authority appears anywhere in Exhibit A. |
| "Compliance is verified by sound testing after construction under the proposed text, not assumed from modeling alone." | §6 requires only an acoustic analysis submitted with the application. No post-construction testing of any kind. |
| "Every generator must meet an enforceable NOx limit of 0.30 lb/MWh", with ultra-low at 0.07 and a graduated "enhanced review" tier | A single tier at 0.5 lb/MWh. The 0.30 limit, the 0.07 threshold, the enclosure requirement, the continuous emissions monitoring and the enhanced-review findings appear nowhere in Exhibit A. |
The ask is narrow: "The justification statement in this packet describes a conditional use permit, a public hearing, post-construction sound testing, and a 0.30 lb/MWh enforceable limit. Exhibit A contains none of those. Which document is the Council adopting tonight?"
One more feature of the current text. The definition of Ultra-Low Emission Generation Technology reads "includes, fuel cells, and linear generators meeting the foregoing standard." There is no "without limitation" and no other technology named, so as written the list is arguably closed and would exclude a future ultra-low technology without a further amendment.51
The cross-reference itself
Exhibit A, the clean enacting text, reads "B. Uses Subject to Conditions (see §15.3.08.060)." §15.3.08.060 is Title 15's Conditional Use Permits chapter. It makes the Planning Commission the land use authority, provides that it "shall hold at least one public hearing," and requires five mandatory findings before approval.2851
Title 15 uses two established forms, and Exhibit A matches neither. An independent sweep of the code found 17 headings reading "Uses Subject to Conditional Use Permit (see §15.3.08.060)", where the cross-reference carries the hearing and findings machinery, and 16 separate bare "Uses Subject to Conditions" headings, none of which carries it.2851 Exhibit A creates a third form that exists nowhere else in the code: the "Conditions" label attached to the Conditional Use Permit cross-reference. That is the anomaly, and it is a residue of the heading it replaced.
The redline settles what a string search could only suggest, and it is the strongest evidence in this report. Packet page 113 carries the amendment as tracked changes. Rendered and read at the pixel level, because strikethrough does not survive text extraction, the drafters struck "conditional use" in four separate places and inserted "conditions" in its place:51
TABLE 14
| Redline, packet p.113 | Effect |
|---|---|
| "Subsection C (Uses Subject to | the subsection is retitled |
| " | heading changed, cross-reference left in place |
| "in support of permitted and | removed from the purpose clause |
| "applies to all Onsite Power Generation Facilities | "approved as a conditional use" struck |
That is not drafting ambiguity. It is a deliberate, systematic removal of conditional-use status from every operative clause, and Exhibit A confirms the result.
The surviving "(see §15.3.08.060)" is therefore best read as residue of the heading struck around it, not as deliberate incorporation. The by-right reading is the likely one, and the Council should know that is what it is voting for. Deleting the stray cross-reference is a one-line amendment that would settle it.
Two more dangling references point the same way. §7 requires operating within emission rates "demonstrated under subsection C", but Exhibit A has no lettered subsections: the single biggest credit this report gave staff, making emission rates enforceable as a zoning condition, hangs on a reference to a subsection that does not exist. And §13's two-site quota identifies uses "as identified in §15.3.16.120(C)", after the same ordinance renumbers that subsection to (B). Three unresolved cross-references, all inside the text being enacted.51
Why this is the right question and not a gotcha. There are two readings and they lead to opposite outcomes. Under surplusage, the cross-reference is a leftover, courts disregard it, the use is purely administrative, and the entitlement runs with the land with no future hearing. Under incorporation by reference, "(see §15.3.08.060)" imports the CUP chapter's procedures, every future applicant gets a Planning Commission hearing and findings, and the ordinance is far stronger than it appears.28
Exhibit A's heading reads "Uses Subject to Conditions" but cross-references §15.3.08.060, the Conditional Use Permit chapter, which requires a Planning Commission hearing and five findings.2851 That cross-reference appears in no other "Uses Subject to Conditions" heading in Title 15. Which controls? And §7 references "subsection C" while §13 references §15.3.16.120(C), both of which this ordinance renumbers. Will these be corrected before adoption?
Nobody can object to that question, and either answer is worth having. "Surplusage" tells the Council on the record that it is granting a permanent by-right entitlement, which is the single fact this whole review exists to surface. "Incorporation" means the protections are real and the ordinance is considerably stronger than its critics allow. This ask rests on the enacting text itself, which is why it holds regardless of what anyone intended.
10. The air permit is not issued, and the comment window closes after the vote
Volition's live website states "Permit Status: Approved." Its August handout states "Utah DEQ issued the permit in 2026."61 The 05 AUG deck told the Planning Commission a permit "has been approved." All three are wrong, and the state's own document says so in terms.
DAQE-IN163550001-26 is an Intent to Approve, issued 4 AUG 2026 by the Utah Division of Air Quality, signed by the Division's New Source Review Section Manager. Its cover letter: "The attached document is the Intent to Approve (ITA)… The ITA is subject to public review. Any comments received shall be considered before an Approval Order (AO) is issued." And its Public Notice Statement: "Air pollution producing sources and/or their air control facilities may not be constructed, installed, established, or modified prior to the issuance of an AO by the Director… The proposed conditions of the AO may be changed as a result of the comments received."
TABLE 15
| Event | Date |
|---|---|
| Intent to Approve issued | 04 AUG 2026 |
| Volition presents to City Council | 04 AUG 2026 |
| Volition presents to Planning Commission | 05 AUG 2026 |
| Notice published, The Daily Herald | 06 AUG 2026 2 |
| Council votes on the text amendment | 18 AUG 2026 20 |
| Deadline to request a DAQ public hearing | ~21 AUG 2026 228 |
| Comment period closes; earliest an AO could issue | 05 SEP 2026 228 |
The Council is being asked to grant a permanent by-right entitlement eighteen days before the air permit that governs the facility can become final, and three days before the public can still demand a hearing on it.28
The applicant's website says the air permit is approved. The state's document is an Intent to Approve dated 4 August, with a comment period open until 5 September and conditions that may still change.28 Why is the city voting on the zoning before the permit is final?
What the permit actually contains, and it is worth stating fairly. The facility is permitted as 1,210 Bloom Energy Server 6.5 units, 393.25 MW combined nameplate, SIC 4911 Electric Services, classified New Minor Source, with no applicable federal standards.1
TABLE 16
| Pollutant | TPY | Equals Bloom's published rate at full output? |
|---|---|---|
| CO2 equivalent | 1,434,855 | ✓ 378 kg/MWh, to 0.04% 13 |
| Carbon monoxide | 22.39 | ✓ 0.013 lb/MWh, to 0.01% 13 |
| Nitrogen oxides | 5.17 | ✓ 0.003 lb/MWh, to 0.05% 13 |
| Volatile organic compounds | 17.22 | ✓ 0.01 lb/MWh, to 0.03% 13 |
| PM10 / PM2.5 | 0.12 / 0.12 | — Bloom publishes no PM figure 1 |
| Sulfur dioxide | 0.01 | — Bloom says "negligible" 1 |
| Total HAPs | 0.29 | n/a 1 |
Every criteria-pollutant limit is the manufacturer's datasheet rate applied to the full nameplate for all 8,760 hours of the year. That is conservative on utilization and carries no margin at all above the vendor's specification. There is no degradation allowance and no measurement uncertainty.43 If the units do not hold their published rates, the facility is out of compliance immediately.
And the handout's carbon figure is honest.61 "Under 1.43M tons of CO2e a year at full build" traces exactly to the permit's 1,434,855 TPY.1 Volition is publishing its own permit's potential-to-emit number, which is larger than this report's operating estimate of roughly 800,000 to 980,000 metric tons at the 75% utilization the Volition representative stated. Both are correct at their stated basis. Quoting either without the basis is not.
11. Why the by-right question matters far more here than it normally would
Utah enacted S.B. 132 (2025), "Electric Utility Amendments", Laws of Utah 2025, ch. 318, effective 7 May 2025, creating Utah Code Title 54, Chapter 26. It defines a new regulated category at 54-26-101(1):1244
"closed private generation system", electric generating facilities and associated transmission infrastructure that "(a) is not connected to and operates independently from the transmission system of a qualified electric utility, cooperative utility, municipal utility, or other utility; (b) serves one or more customers with a minimum cumulative electrical demand of 100 megawatts; and (c) serves one or more large load customers through direct connection."12
That is a verbatim description of this facility, at 2.5× the statutory threshold. And 54-26-504 provides that such systems "are exempt from commission oversight or regulation as a public utility."44 A conventional 250 MW power plant in Utah passes through several independent public-interest gates.51 This one passes through almost none:
TABLE 17
| Reviewer | Jurisdiction over this facility |
|---|---|
| Utah Public Service Commission | None. Expressly exempt, 54-26-504 44 |
| The electric utility | None. No interconnection is requested. That is the point of the design |
| Utah DAQ | Ministerial. A minor-source approval order is issued when thresholds are met. DAQ does not weigh siting, noise, heat, water, traffic, or land use |
| FERC | None. No transmission nexus |
| Spanish Fork City land use | The only discretionary public-interest review this facility will ever receive |
Title 54 Chapter 26 is a Public Utilities framework, silent on municipal zoning; it neither preempts local land-use authority nor supplies a substitute for it.44 So the entire public-interest review of a 250 MW industrial power plant reduces to one thing: the Spanish Fork zoning decision. And §15.3.24 as drafted converts that decision into an administrative permit issued over a counter, with no hearing and no findings.112851
This is not an argument that Volition is dangerous. It is an argument about where the only remaining valve is. The off-grid design that makes this project genuinely attractive is the same design that removes it from every regulator except the city. Islanding is a benefit and a jurisdictional exit at once, and only one of those is in the deck. It also disposes of the most common rebuttal at hearings, "the state and DAQ will regulate this anyway": for a closed private generation system, the state has affirmatively legislated that it will not.1228
And the exemption is not incidental to the design. It is contingent on it. 54-26-101(1) defines a closed private generation system as one that "is not connected to and operates independently from the transmission system of a qualified electric utility."12 Interconnection is physically available: a 345 kV hub sits under a mile due north of the parcel.4043 Tying into it would satisfy the one condition that currently removes this facility from Public Service Commission jurisdiction, and would add a FERC-jurisdictional interconnection queue and years of system-impact study on top.44
The islanded design is why there is no rate impact, no socialized transmission cost, no substation build and no interconnection queue. It is also what leaves Spanish Fork land use as the only discretionary review, and it is a choice the operator can revisit: nothing in the statute requires the facility to stay islanded, only §5 does. That makes §5 the load-bearing provision in the whole text. Worth asking what happens to the permit if a successor applies to interconnect.
And the reporting backstop does not exist. S.B. 282 (2026) would have required an annual electricity- and water-consumption report from the generation provider to the host municipality; it failed, confirmed two ways from primary sources.4449 H.B. 585 (2026), which would have required data centers to disclose "the percentage self-generated" and "the type of generation facility and fuel source," also failed.50 So there is no state-law disclosure obligation covering this facility's energy, emissions, or water. The "annual public reporting" covenant Volition volunteered, and which §15.3.24 omits, has no statutory backstop whatsoever. If it is not in the ordinance or the development agreement, it does not exist.11
Is by-right an outlier in Utah? No. It is the norm.
TABLE 18
| Jurisdiction | Mechanism | MW cap | Data-center-specific standards |
|---|---|---|---|
| Eagle Mountain (hosts Meta) | Permitted (P), Industrial Zone, §17.40.020, administrative | None | None. Ch. 17.75 Special Use Standards has zero data-center entries |
| Bluffdale (hosts the NSA facility) | Permitted (P) in HC, RC, I-1, I-2, Table 11.350.020, administrative | None | None. No footnote on the use row 15 |
| Lehi | By silence. No "data center" in the use table or definitions; falls under generic warehousing | None | None |
| Saratoga Springs | No provision; unlisted uses "strictly prohibited" absent PC hearing + Council approval | N/A | N/A 28 |
| Utah County, unincorporated | Affirmatively prohibited. §1.28: uses "not expressly permitted… are hereby declared to be expressly prohibited" | N/A | N/A |
| Box Elder County | 180-day moratorium, ~10 JUN 2026 | N/A | N/A |
| Spanish Fork §15.3.24 | Permitted, administrative | 500 MW/site, 2 sites citywide | 65/55 dBA, cooling method, emissions standard, electrical isolation, water condition, decommissioning, battery fire safety 11 |
| West Jordan (hosts Novva, Aligned) | Permitted (P), Title 13 Ch. 5 Art. F, M-P zone only; unlisted in M-1/M-2, and unlisted uses "shall not be allowed" | None | None attached to the use |
Two conclusions follow, and they point in opposite directions.
1. On the mechanism, Spanish Fork is the Utah norm. Eagle Mountain and Bluffdale permit data centers administratively by a plain "P" in a use table; Lehi permits them by silence; Eagle Mountain moved toward this posture recently, Ordinance O-40-2024, 3 SEP 2024, titled in part "REMOVING CONDITIONAL USES." The criticism that Spanish Fork is doing something procedurally unusual does not survive.28
2. On the substance, Spanish Fork's ordinance is the most regulated of any Utah jurisdiction examined, by a wide margin. It is the only one with a megawatt cap, a citywide quota, a data-center-specific noise standard, a cooling-method restriction, an emissions requirement, an electrical-isolation mandate, a water condition, or a decommissioning provision. Eagle Mountain and Bluffdale host operating data centers under codes that impose none of those.
That is a genuine credit to Spanish Fork staff: they wrote more protection into this ordinance than any Utah city that already has data centers, before the first one arrived. The criticism that remains is not that §15.3.24 is weak by comparison. It is that its specific gaps, no heat standard, no post-construction noise verification, no decommissioning security, no potential-to-emit cap, are real, and three of them are gaps the applicant's own filing describes as already filled.11
One point of context. Among jurisdictions that considered this question recently, Saratoga Springs, Box Elder County, Loudoun County VA, every one moved toward more discretion, while Eagle Mountain's and Bluffdale's permissive treatment predates the current wave.51 That distinction is real, but it is weaker than the cross-reference question and should not lead.
12. Four state-law facts nobody in the Spanish Fork record has mentioned
All four come from enrolled bill text read in full.
1. The fuel cells are already sales-tax exempt, and the rest may be too. Utah Code 59-12-104(80) exempts "sales of a fuel cell as defined in Section 54-15-102," unconditionally and independent of anything about data centers.45 The Bloom array, plausibly the largest single equipment line in the project, is exempt on its own terms. Separately 59-12-104(84) exempts equipment bought by a "qualifying data center," which 59-12-102(109) defines as a facility that "(c) is a new operation constructed on or after July 1, 2016; (d) consists of one or more buildings that total 150,000 or more square feet." The 1,054,000 sq ft clears (d); prong (c) is genuinely uncertain, since this is adaptive reuse of a building the leasing listing dates to 1998.55 The councilmember weighed "$50 million existing assessed value" against "$4 billion in equipment investment" (04 AUG minutes p. 69) with no offsetting entry, and sales and use tax on a $4B purchase is not a rounding error.4551
Does this facility qualify under 59-12-104(84) given the 1998 building, and what sales and use tax does the city forgo?45 Do not assert a dollar figure. The fuel-cell exemption is certain; the data-center exemption's reach into a reused building is not.
None of this contradicts "no incentives requested." These exemptions are automatic, and H.B. 507 (2026) provides at 11-41-202(2)(e) that "a sales and use tax exemption described in Section 59-12-104 does not constitute an incentive."4548
2. Utah's only data-center disclosure law is keyed to water, and this design sits under it. H.B. 76 (2026) created Utah Code 73-5-8.3, requiring that "before a land use authority… approves a land use application for a new large data center, the land use authority shall notify" the Divisions of Water Rights and Water Quality and the water provider.47 "Large data center" is defined by annual withdrawal of 75 acre-feet or more. Volition's 250,000 gal/yr is 0.77 acre-feet. Two orders of magnitude below the trigger.51
Read both ways: it is real evidence for the closed-loop design, and it means the state's only data-center notification regime does not reach this project. 73-5-8.3 expressly contemplates "generation by the operator of the large data center of energy to power a specific facility," so the statute knows self-generation exists and still gates on water. Combined with the failure of S.B. 282 and H.B. 585: no Utah statute requires this facility to report its energy use, emissions, self-generation, or water.474950
3. An NDA with the city would now be a protected record. S.B. 318 (2026) would have prohibited municipal NDAs with prospective data centers and voided existing ones. It failed.44 H.B. 507 did the opposite, amending 63G-2-305(2)(b) to protect "confidential economic development information… that takes the form of a nondisclosure agreement between a person and a governmental entity exploring an economic development opportunity." The Volition representative told Council conversations began "around October or November" (p. 64), roughly nine months before the application surfaced.4648 Any such NDA is now statutorily shielded from GRAMA, a live constraint on the records strategy in open-questions.md.
Is there a nondisclosure agreement between the city and Volition or any affiliate? The existence of one is answerable without disclosing its contents.
4. A mechanism now exists to divert the tax base being promised. H.B. 507 also enacted Title 63N, Chapter 3a, Part 4, creating "Regionally Significant Zones with Energy Implications." Under 63N-3a-402(3)(b) a zone proposal may "(i) capture up to 60% of the property tax increment… and (ii) divert up to 100% of personal property tax revenue" generated within it.48 The entire $40M/yr pitch rests on personal property tax on equipment. From 6 MAY 2027 a municipality may generally "not offer an incentive for a large load data center that is not located within a zone,"51 pushing large projects toward the mechanism. Nothing suggests anyone has proposed a zone here, but the fiscal case Council was shown treats the $40M as settled municipal revenue while state law contains a documented pathway to route most of it elsewhere in a later proceeding.
13. The $40M/year does not mean what the room heard
The year-one arithmetic is sound, and almost none of the number survives contact with who receives it and how fast it depreciates. The figure is gross, and gross is what an applicant quotes. Neither correction below challenges Volition's honesty, the slide names "the largest share flowing to Nebo School District" and its footnote states the rate is "declining as personal property depreciates."34 They are corrections to what the room is likely to have heard.
Correction 1: 75% of it is not the city's
Utah County Assessor, parcel 67:228:0003, Tax Area 150.10 The combined certified rate for tax year 2026 is 0.009563:15
TABLE 19
| Taxing entity | Rate | Share of the levy | Year one, at the claimed $40M gross |
|---|---|---|---|
| Nebo School District | 0.007190 | 75.2% 15 | ~$30.1M |
| Utah County, local and state assessing, water | 0.001415 | 14.8% 15 | ~$5.9M |
| Spanish Fork City | 0.000958 | 10.0% 15 | ~$4.0M |
| Combined | 0.009563 | 100% | ~$40M |
A gross $40M/year is roughly $4.0M/year to Spanish Fork City.43 The rest is real public revenue and Nebo School District is a legitimate beneficiary, but the number was presented in a Spanish Fork Council chamber, weighing a Spanish Fork land-use decision, without that breakdown.34
One commitment worth pinning down, from the 23 JUL marketing video: "A share of every site's revenue flows straight back into the community that hosts it." A revenue-share is materially stronger than a flat ">$500,000," because a percentage scales with the facility and a flat figure does not. Ask which form the development agreement takes.
The tax base is a community benefit, not a city line item
Nebo's share alone is more than five times Spanish Fork City's entire annual property tax revenue from every parcel in the city, $5,885,340.59 At recent Utah costs that is a new elementary school every year, or a new high school every three to four years, against Utah high school builds of $77.5M to $145M.74 Nebo School District and Utah County have a direct and substantial interest here, and neither has appeared in the record.
The direct community contribution is larger than it sounds
Volition has committed to more than $500,000 a year in direct community contributions, described in the 23 JUL video as "a share of every site's revenue."1651 Against what the city collects today:
TABLE 20
| To Spanish Fork City, per year | |
|---|---|
| The city's largest commercial taxpayer, Longview Fibre / WestRock | $33,444 |
| The eleven largest commercial taxpayers, combined | $249,032 |
| Volition's committed community contribution alone | > $500,000 |
The proposed contribution by itself is 15× the city's property tax take from its single largest commercial taxpayer, and twice what the city receives from the eleven largest combined.5773 That is before a dollar of property tax.
COMMITTED, NOT EXECUTEDVolition's CEO has stated repeatedly and on the record that this contribution will be included in the development agreement, and this report treats that as made in good faith and expected to hold.1651 But no development agreement has been published or signed, and the text amendment does not require one.51 The remaining question is form, not intent: ask that it be written as the revenue share the video describes rather than a flat figure, since a percentage scales with the facility and a flat number does not, and ask for a floor under the tax projection in the same instrument.
Correction 2: the $40M is a floor, not a ceiling, and it depreciates slowly
The $4B figure does not include the servers. Volition's own project page states the investment covers "retrofit, fuel cells, electrical, fire, security, and engineering."4 Compute hardware is not in that enumeration. Volition builds and powers the facility to the rack; the tenant installs the servers, and that equipment is additional taxable value on top of the $40M, in an amount nobody can state. So $40M/year is the applicant's expected minimum, not its total.
That changes which depreciation curve governs, and it runs in the proposal's favor. Utah Admin Code R884-24P-33 sets percent-good schedules by class, and two classes behave completely differently:14
TABLE 21
| Year | Class 12, computer hardware | Class 27, electrical generating equipment 14 |
|---|---|---|
| 1 | 62% good, $23.7M | 97% good, $37.1M |
| 2 | 46%, $17.6M | 95%, $36.3M |
| 3 | 21%, $8.0M | 92%, $35.2M |
| 4 | 9%, $3.4M | 90%, $34.4M |
| 5 | 7%, $2.7M, the floor | 87%, $33.3M 14 |
| 10 | 7%, $2.7M | 74%, $28.3M 14 |
(Each column models the full $4B in that class, at the 2026 combined rate of 0.009563.)1415
Volition's $4B sits overwhelmingly on the durable side. Fuel cells, electrical, fire and security are generation equipment, and the retrofit is real property, reassessed at market rather than run down a percent-good schedule. None of it is Class 12, because the compute is not Volition's, and the base holds 74% of its value at year ten.
Two features of the plan push the same direction. The Volition representative told Council the Bloom equipment would undergo "a phased upgrade approximately seven or eight years after installation", paid monthly in advance for a full "swap out and retrofit."51 Replacement equipment is assessed as new, resetting the curve. And tenant compute refreshes on its own cycle, each refresh re-entering the roll at 62% good. The fast-depreciating asset is also the one that gets replaced most often.
The remaining uncertainty is upside, not downside, because nobody can size the tenant equipment. Two things are worth asking for, neither adversarial. The tax pro forma, assumed class split, refresh cycle, and projected assessed value in years 1, 5 and 10; the councilmember asked for exactly this on 04 AUG, that "the underlying figures needed to be clearly documented."51 And a revenue floor in the development agreement, which converts a projection into a commitment and costs the applicant nothing if the projection is sound.
One caveat on the schedule itself. Class 27 is defined as "plants designed to generate electrical power using turbogenerators."14 Solid-oxide fuel cells are not turbogenerators. If the Assessor classes them elsewhere the curve changes, which is another reason to ask for the pro forma rather than assume it.
One thing not to do: do not net the sales-tax exemption against the property tax. 59-12-104(84) is a sales and use tax exemption only. It does not touch property tax, and conflating the two produces a wrong number in both directions.45
Correction 3: what $40M/year means against what these businesses actually pay
This is public record, and it should be quoted rather than computed. Utah County publishes the tax actually billed on every parcel, by year; 2025 is the most recent complete year.57
TABLE 22
| Taxpayer, owner of record56 | 2025 market value | 2025 tax billed | Multiple to reach $40M |
|---|---|---|---|
| Longview Fibre / WestRock, 2200 N Main | $34,660,500 | $333,850 | 120× |
| Young Living Essential Oils | $31,884,700 | $316,232 | 126× |
| Pheasant Run Properties, 1804 N 300 W | $28,389,100 | $273,444 | 146× |
| Nature's Sunshine Products | $28,306,000 | $272,643 | 147× |
| IHC Health Services, Spanish Fork Hospital | $125,655,900 | $217,857 | 184× |
| Wal-Mart Real Estate Business Trust | $21,922,560 | $213,291 | 188× |
| Hydro Extrusion USA, the city's largest air source | $21,984,800 | $211,758 | 189× |
| Sunroc Corporation | $18,912,100 | $182,161 | 220× |
| CDL Real Estate Holdings, 2600 N Main | $18,904,200 | $182,085 | 220× |
| Costco Wholesale | $18,869,700 | $181,753 | 220× |
| Rock Hollow Properties, 2102 N Main | $10,467,500 | $100,823 | 397× |
The eleven largest commercial taxpayers in Spanish Fork paid $2,485,898 between them in 2025. Volition's claimed $40M is sixteen times all of them combined.57
The hospital is not the benchmark it looks like: the city's most valuable property pays less than five other businesses, an effective 0.001734 against the 0.009632 everyone else pays, the standard Utah charitable exemption.5758 The correct benchmark is WestRock at $333,850, the largest property tax bill in Spanish Fork.
And the city's own revenue is the number that matters most
Spanish Fork City's audited FY2025 statements report total property tax revenue of $5,885,340, against $5,741,117 the year before.59 That is the whole city: every home, every business, every parcel.
TABLE 23
| Amount | |
|---|---|
| Spanish Fork City's entire annual property tax revenue, audited | $5,885,340 |
| The eleven largest commercial taxpayers, combined | $2,485,898 |
| Volition's claimed gross levy | ~$40,000,000 |
| Of which the city itself would keep, at its 10.0% share of the levy | ~$4,010,000 |
Two true statements, and the Council needs both. Volition's gross claim is 6.8× the city's entire property tax revenue, which is why the number sounds unreal in a Council chamber. But the realistic municipal benefit is roughly $4.0M a year, which would raise the city's own property tax revenue by about 68%, a very large benefit, and smaller than the headline by a factor of ten. For scale, $4.0M is roughly 120× what the city currently collects in property tax from its largest commercial taxpayer, which bills $33,444.1559 Setting $40M beside $5.9M compares a total against a share.
Two rates are in play and are not interchangeable: the 2026 certified rate of 0.009563 for projections, and the 0.009632 actually applied to 2025 bills for comparisons against real billed dollars.155773 At the certified rate $4 billion produces $38.3M, so $40M is sound as a gross year-one figure.
The assessed-value baseline checks out, the acreage in testimony does not
The councilmember's "approximately $50 million existing assessed value" is confirmed: $50,898,400 total assessed for 2026, owner of record WDC Industrial Utah Owner LP.51 An $81,000,000 figure in the parcel abstract is a trust deed, not a sale price: Utah is a non-disclosure state.
The Volition representative told Council the building "sat on approximately 25 acres."51 The Assessor record shows 69.478641 acres, corroborated at 69.09 by computing the area of the state's parcel polygon.10 ~23–25 acres is the single-story footprint, not the parcel, leaving roughly 44 acres of open ground for the fuel-cell field, transformers, switchgear and cooling plant. The site is physically ample. It was the testimony that was wrong, not the plan.55 But note what else 44 acres means: the ordinance's 500 MW cap is not constrained by land. At Bloom's published density 500 MW needs roughly 14–18 acres of yard, so the parcel can hold the full entitlement twice over.1143
14. How Utah County property taxes are actually calculated
Every argument above about the $40M, and most of the neighborhood argument about property values, runs through a mechanism almost nobody in the public record has described. It is entirely statutory, it is not what most people assume, and getting it right changes what the Council should say about revenue.
The chain, step by step
TABLE 24
| When | What happens | Authority |
|---|---|---|
| 1 JAN | Lien date. All tangible taxable property is assessed at fair market value as of 1 January, at a uniform and equal rate. | 59-2-103(2) 66 |
| Every year | The assessor annually updates values using a certified computer assisted mass appraisal system driven by a "systematic review of current market data." The mandatory annual all-parcel update applies to residential property. | 59-2-303.1(2), (1)(a)(ii) 67 |
| Every year | The State Tax Commission runs assessment studies measuring assessed against market value, then orders each county to factor its assessment rates. Factoring "may include an entire county, geographical areas within a county, and separate classes of properties." | 59-2-704(1), (2) 68 |
| At least once every 5 years | The assessor completes a detailed review of the property characteristics of each parcel. This is the only step that involves anyone actually examining your property. | 59-2-303.1(3)(a), (b) 67 |
| Value adjustment | A qualifying primary residence receives a 45% reduction in value, on no more than one acre per residential unit. | 59-2-103(3), (5) 66 |
| Before 1 JUN / by 13 JUN | The assessor delivers aggregate valuations to the auditor, who transmits the certified tax rate to every taxing entity. | 59-2-924(2), (3) 69 |
| On or before 22 JUL | Every owner is mailed the Notice of Property Valuation and Tax Changes, showing value, taxable value, any proposed increase, the hearing, and the appeal deadline. | 59-2-919.1(1), (2) 71 |
| 15 SEP, or 45 days after that notice, whichever is later | Deadline to appeal to the county board of equalization. | 59-2-1004(3)(a) 72 |
| Autumn | Entities set final rates; the treasurer issues the tax notice, which must state whether the property may be subject to a detailed review next year. | 59-2-1317(2) 72 |
That disposes of the most common objection to the system, which is that assessors cannot possibly be driving every street in the county. They are not, and the statute never asks them to. Values move through mass appraisal and Commission-ordered factoring applied to geographic areas, and human inspection of an individual property is a once every five years event.676872
The certified tax rate is the part almost nobody knows, and it is the whole answer
Utah has been revenue-based rather than rate-based since 1985. The statute is blunt:
"Certified tax rate" means a tax rate that will provide the same ad valorem property tax revenue for a taxing entity as was budgeted by that taxing entity for the prior year, calculated by dividing the ad valorem property tax revenue that a taxing entity budgeted for the prior year by the current year's adjusted aggregate taxable value.69
Revenue is fixed first. The rate is whatever number produces it. A taxing entity may not levy above its certified rate, except during a truth-in-taxation exemption period, unless it advertises, mails notice, and holds a public hearing.70
When values across the county go up, the rate mechanically comes down, and that is directly observable in Spanish Fork's own records. Four large commercial parcels, four owners, five consecutive years, all in Tax Area 150 carry an identical effective rate to six decimals in every year, because the rate belongs to the tax area and not the parcel; a fifth parcel in a different area returns a different rate, which confirms the reading:73
TABLE 25
| Tax year | Combined effective rate, Tax Area 150 | Change |
|---|---|---|
| 2021 | 0.011230 | |
| 2022 | 0.009881 | −12.0% |
| 2023 | 0.009691 | −1.9% |
| 2024 | 0.009702 | +0.1% |
| 2025 | 0.009632 | −0.7% |
The rate fell 14.2% in four years. Nobody voted for a tax cut. That is Truth in Taxation operating exactly as written.
So why did an announcement next door not raise your taxes
Because rising value is not the thing that raises your bill. What raises your bill is your value rising faster than the average inside your taxing entity, or the entity voting an increase after a noticed hearing. The same parcels show it:73
TABLE 26
| Parcel | Taxable value, 2021 to 2025 | Actual tax billed, 2021 to 2025 |
|---|---|---|
| Costco Wholesale | +44.7% | +24.1% |
| Longview Fibre / WestRock | +57.3% | +34.9% |
| Hydro Extrusion USA | +37.4% | +17.9% |
| Nature's Sunshine Products | +34.8% | +15.6% |
Every one gained a third to a half in assessed value and none saw its bill rise anywhere near that much. The gap is the certified rate falling underneath them.
Three consequences to carry to the podium: a new landmark, temple, park, school or data center does not raise your taxes by existing, only by making your property appreciate faster than the county average; an announcement is not evidence of value, since the annual update runs on current market data and factoring on assessment studies, so a change appears only once transactions demonstrate it;6768 and the reverse attribution is the common error, people see the bill move, look at what changed nearby, and connect the two, when the bill moved because of a countywide ratio study and a divisor.
The finding that matters for this amendment
New growth is deliberately excluded from the certified rate denominator. The statute subtracts eligible new growth from the value the prior year's revenue is divided by, and "locally assessed new growth" expressly excludes any change in value "as a result of factoring in accordance with Section 59-2-704, reappraisal, or another adjustment."69 It captures new construction, not market drift. Two consequences follow, and the room needs both:
Revenue from a new facility is additive. It sits on top of the prior year's budgeted revenue, requires no Truth in Taxation hearing, and does not come out of any existing taxpayer's pocket.6970
FALSE, and it should stop being said. "The data center will lower my property taxes" is not what the formula does. The certified rate is computed before new growth is added back, which is the entire point of excluding it. Nothing in Section 59-2-924 reduces an existing owner's bill because a new taxpayer arrived.69
One carve-out worth an ask. Section 59-2-924 already excludes, from both revenue and aggregate taxable value, personal property that is semiconductor manufacturing equipment.69 The Legislature has already removed one class of high-value technology equipment from this machinery, and the great majority of Volition's projected $4B is personal property of a broadly similar character.
Does the development agreement address what happens to the city's revenue expectation if the Legislature later extends a comparable exemption to data center equipment? That is not speculation about a hypothetical statute. It asks whether the agreement anticipates a carve-out the Legislature has already granted once, in this exact section.
15. Claims that fail
TABLE 27
| # | Claim | Verdict |
|---|---|---|
| 1 | CO2 equals "three or four diesel trucks" | Split verdict, and the split is the finding |
| 2 | The emissions comparison table (P-08) | MISLEADING by ~1,100× |
| 3 | "Equal to 4–5 semi trucks per year" | Unfalsifiable as written |
| 4 | "~13 W/m²" of heat | Misleading by juxtaposition |
| 5 | The Novva proof point | FALSE |
The carbon numbers these claims are measured against
Bloom's February 2026 datasheet for the ES 6.5 publishes 679–833 lb CO2/MWh, and that printed figure reconciles to 0.1% with the datasheet's own heat rate through EPA's standard natural-gas carbon factor.325 Utah DAQ's Intent to Approve puts the facility's potential CO2e at 1,434,855 tons per year (DAQE-IN163550001-26, 4 AUG 2026).143 At the 75% utilization the Volition representative stated, the realistic figure is ~796,000–977,000 metric tons/yr. Methane in a solid-oxide fuel cell yields CO2 as its primary carbon product: suppressing combustion eliminates thermal NOx, not carbon.51 Upstream methane leakage adds 76,000–125,000 t CO2e.43
The estimate is more likely low than high. In the one case where a state regulator measured Bloom units in the field, Delaware found a 24-month average of 823 lb CO2/MWh against Bloom's advertised 773 (NBC Bay Area, 25 JUN 2015), and a separate installation, AC Transit, held the advertised rate only for the first three of 22 months.52 That is a decade old and predates this platform, but it means the datasheet figure is a floor. Even at 823 lb/MWh Bloom still beats the Utah grid, which EIA puts at 0.601 metric tons CO2/MWh for 2024, about 1,325 lb/MWh.27 The criticism is the gap between marketing and measurement, not the absolute number.
1. CO2 "the same amount as three or four diesel trucks"
The answer depends entirely on scope, and no scope is stated anywhere. On total facility CO2 the permit's 1,434,855 t/yr against 3–4 trucks at 171.5 t each fails by 1,900–2,500×.143 On criteria pollutants converted to CO2-equivalent, the basis Volition actually described, short-lived climate forcers carry published indirect GWP100 values, several negative (NOx nets between −11 and −108 per kg, SO2 around −40, while CO is +1.9 and VOC +4.5), and applied to the five permitted pollutants the sum lands between roughly −400 and +110 t CO2e against 3–4 trucks at 515–686 t. On that basis the claim is defensible, even conservative.
The two readings differ by a factor of roughly 5,000.43 The basis used is the air permit's scope, five criteria pollutants with CO2 excluded by design, which omits the 1,434,855 t/yr the permit itself authorizes, from oxidizing 19–24 billion cubic feet of methane.1 That is 99.98% of the facility's greenhouse footprint. Not a lie. An unstated basis that swings the answer by three and a half orders of magnitude.
One carbon claim holds up cleanly. "The lowest-available carbon at this scale" is correct, and the honest framing is the one Volition should have used:
TABLE 28
| t CO2/MWh | Annual at 393.25 MW and 75%1 | |
|---|---|---|
| Volition | 0.343 | ~886,000 t 343 |
| Novva-style gas engines | 0.483 | ~1,248,000 t 43 |
| Utah grid average | 0.601 | ~1,553,000 t 2743 |
Roughly 29% cleaner than on-site gas engines and 43% cleaner than the Utah grid, per unit of compute. Both things are true at once: this adds roughly 890,000 tons of CO2 to Utah County that does not exist today, and it is the lowest-carbon way to run that compute given what actually gets built. Telling a council it equals four trucks throws away a real advantage.
2. The emissions comparison table
Slide P-08 puts a "natural gas reciprocating engine" at ~59,700 tons NOx/yr with no capacity, capacity factor, or basis stated. Utah's own permit for 235.6 MW of exactly that equipment (Novva, DAQE-AN160660003-24) is 51.28 tons/yr, which scales to ~86 tons at this facility's 393.25 MW.131 The "Utah grid average ~2,600" row has no stated basis at all.
The defensible claim is ~10× cleaner than West Jordan and ~45× cleaner than the Millard County facility, with no HAPs and no purchased offsets.32 Inflating that to ~11,500× replaces a verifiable advantage with an indefensible one and hands critics the easiest attack in the record.
3. "Equal to 4–5 semi trucks per year"
The slide states no basis, and the two available fleet baselines differ by roughly 20×.43 What can be said uses only the deck's own numbers: the 04 AUG Council deck puts its stated truck fleet at ≈2 metric tons NOx and ≈50 kg PM2.5/yr (420,000 truck-miles, 65,000 gallons of diesel, internally consistent at 4.76 g NOx/mi and 0.119 g PM2.5/mi).43 Against the facility's 5.17 short tons NOx and 0.12 short tons PM2.5:1
NOx: 4,690 kg ÷ 2,000 kg = 2.3× PM2.5: 109 kg ÷ 50 kg = 2.2×
Two pollutants, computed independently, agree: the facility is roughly 2.2–2.3× the truck fleet the applicant's own deck describes, not four or five trucks out of it. That is a finding about the slide, not about the site. The deck never states what its fleet figure represents, and it cannot be read as the fully tenanted warehouse this report compares against: the building is mostly vacant today and its present truck traffic is very low, so any baseline anchored to current operations answers a question nobody is voting on.51 The comparison that matters is the proposed data center against the fully tenanted distribution warehouse the building was built for, and that one is computed from ITE rates in §6 rather than taken from the applicant. On that basis the warehouse runs 6,396 to 12,849 diesel trip ends a month and the data center none.43
The Planning Commission deck states the same fleet baseline as 101 kg NOx and 4.2 kg PM2.5, understated ~20× and ~12×, and implausible on its face. Understating the fleet makes each truck look cleaner, which makes the equivalence harder to satisfy. The error works against Volition's own argument, the signature of a rushed revision rather than a manipulation. The claim appears only in the 05 AUG Planning Commission deck, not in the 04 AUG deck the city filed.
4. "~13 W/m²" of heat
Over the verified 69.5-acre parcel, 605–742 MW-thermal gives ~2,150–2,640 W/m².1043 To get 13 the denominator must be 47–57 km², well beyond Spanish Fork's entire municipal area. The figure is facility heat ÷ city area, printed beside "Max of +5°F on-site," differing by a factor of ~170–210 in basis. As a city-scale comparison it is coherent; as printed it invites the wrong inference.
5. The Novva proof point
The Volition representative cited Bloom running 50 MW at Novva with Oracle as tenant, the largest single-site Bloom deployment in existence. Refuted across four independent layers: Utah DAQ's approval order (72 gas engines, 37 diesel generators, zero fuel cells), Novva's own 16-release press archive, Novva's Utah marketing page, and Bloom's newsroom.31 The real project is Oracle's "Project Jupiter," up to 2.45 GW of Bloom fuel cells in Doña Ana County, New Mexico, announced 27 APR 2026.24
But the correction runs in two directions. The largest documented single-site Bloom deployment in North America is 73 MW (AWS/Cologix, Hilliard, Ohio, PUCO-approved JUN 2025, under legal challenge by the City of Hilliard); the largest anywhere is the 78.96 MW Shinincheon Bitdream plant in South Korea, operating since 2021.24 At the permitted 393.25 MW, Spanish Fork would be 5.0× the largest fuel cell installation on earth, and 6.3× at the ordinance's 500 MW cap. Volition described this accurately at Council: the closest comparable "was not a Volition facility," only "the same general contracting and engineering team."111
16. Property values, which the evidence addresses better than either side admits
Four studies bear directly on this and none says what either camp claims. The strongest evidence finds no negative effect and often a positive one, while the study conducted nearest a proponent's interest has the weakest numbers of the four.
The best study says proximity is associated with higher prices, not lower
George Mason University's Center for Regional Analysis modeled every 2023 BrightMLS home sale in Northern Virginia, the densest data center cluster on earth, using a hedonic regression that explains 86.7% of price variance.62 Its data center result:
TABLE 29
| Variable | Coefficient, by distance | Significant |
|---|---|---|
| Distance to a data center | −$15,886 | Yes, p < 0.001 |
| Distance to industrial land | +$47,523 | Yes, p < 0.001 |
| Distance to office-zoned land | +$5,737 | Yes |
| Distance to Metro | −$6,251 | Yes |
The sign is what matters here: homes farther from a data center are worth less, not more. The authors state it plainly: "The analysis fails to demonstrate statistical evidence that proximity to a data center negatively impacts housing values."62 And they anticipated the obvious objection. Because data centers usually sit on industrial land, controlling for industrial proximity might absorb the penalty, so they re-ran the model with the industrial variable removed. The data center coefficient stayed negative at −$9,745, R² essentially unchanged at 0.864. The effect survives the objection.
Two more studies point the same direction, with real caveats
Priest, Not In My Back Yard! The Effects of Data Centers on Housing Prices matches Virginia air-permit issuances to ZIP-level house price indices in a difference-in-differences design and reports effects "economically small and slightly positive," with confidence intervals that rule out substantial declines.63 The full text sits behind a CAPTCHA that has failed three times across this review, so only the abstract is verified. Treat it as supporting, not load-bearing.
NBER Working Paper 35194 (Alvarez, Argente, Chow and Van Patten, May 2026) uses a shift-share instrumental-variable design across roughly 3,130 US counties and finds a house price index coefficient of +0.177 (SE 0.028), falling to +0.136 with state fixed effects but staying significant.18 Two limits matter. It is an NBER working paper and explicitly not peer-reviewed, and it is county-level, so it describes what happens to a county's housing market, not what happens to the house across the street.
The study that complicates the picture is the industry's own
Integra Realty Resources examined homes within 1.5 miles of four Indiana data centers from 2021 to 2026, and presented the analysis in support of a zoning variance a developer was seeking.64 The headline is that nearby values rose 42% against 41% countywide. The detail is less flattering: values rose near all four sites, but at Microsoft LaPorte the 1.5-mile increase of +42% lagged the county's +48%, and the favorable average is carried by Amazon New Carlisle alone at +49% against +32%. The method is also thin: 20 Zillow estimated values per location. This is weak evidence in either direction, and it is worth citing mainly because it is the proponent-side study and it does not clearly support the proponent-side claim.
What none of this settles
Every study above measures conventional data centers. None measures one with a 393 MW on-site power plant, because essentially none exists. Heat, gas throughput and continuous generation noise appear in none of these samples.
The argument specific to this site, and it is a fair one
The counterfactual here is not farmland. It is an operating one-million-square-foot distribution warehouse, and that matters on these very coefficients.55 GMU's industrial-distance penalty is $47,523, three times the data center coefficient and opposite in sign.62 The industrial penalty is already priced into every home near this site, because the site is already industrial.
A 393 MW generating plant does not stop being industrial land. Volition's facility may keep the industrial coefficient rather than shed it, and no study in this literature can tell the Council which. The traffic and water reductions are real and documented. The property value effect is genuinely unknown for this specific configuration, and anyone claiming certainty in either direction is ahead of the evidence.
One finding worth carrying to the podium for a different reason
The same NBER paper that finds house prices rise also finds electricity prices rise, coefficient +0.009, significant at the 1% level across every horizon tested.18 A competing study reaches the opposite conclusion: Watten, Bistline and Blanford estimate that data centers caused average US retail rates to fall modestly between 2015 and 2024, though they caution that "future supply constraints could reverse the effect."65 Two of the three authors are at the Electric Power Research Institute, an industry-funded body, which the Council should weigh.
The literature genuinely disagrees on ratepayer impact, and this is the one dimension where the Spanish Fork proposal is unusually well positioned. A permanently islanded facility that draws nothing from the municipal grid cannot raise Spanish Fork ratepayers' bills through the mechanism either study is measuring.11 That is a real advantage and the applicant has not made enough of it.
17. Claims that hold up
- NOx 5.17 tpy is the permitted limit, and it is exactly Bloom's datasheet rate at full output. 0.003 lb/MWh × 393.25 MW × 8,760 h = 5.17 tpy, matching DAQE-IN163550001-26 to 0.05%.1343 The same is true of CO (22.39) and VOC (17.22). The permit assumes 100% capacity factor, which is conservative, but it carries no margin whatsoever above the vendor's published specification.1 VOC exceeding NOx by ~3× is correct SOFC behavior, not an error.
- "<65 dBA at 10 ft per unit", verbatim from Bloom's datasheet including the measurement distance, and Volition disclosed the limitation itself, to the Council, in print. The footnote on that slide reads: "PER-UNIT SPEC FROM DATASHEET; ARRAY-WIDE ACOUSTIC MODELING AND AN ENFORCEABLE NOT-TO-EXCEED LIMIT ARE BEING COMMISSIONED BEFORE FINAL APPROVAL." The ordinance requires neither the array-wide modeling nor any post-construction check.311
- Water arithmetic, 500,000 gal fill ≈ 2.6 households and 250,000 gal/yr ≈ 1.3, sourced to the Central Utah Water Conservancy District's 155 gal/person/day filing and Census household size, correctly applied.51
- "+5°F max on-site" and "<1°F beyond a quarter mile", both plausible under light wind.
- "Less than half of what Lake Side Power Plant produces" held at the 250 MW rack load but fails at the permitted 393.25 MW: 605–742 MW-thermal is 46–56% of Lake Side's ~1,315.1334351 That slide is still the only one in the deck that discloses its own methodological limitation.
- ~$40M/yr in year one, arithmetically sound. $4B × 0.95% = $38M.51
- "We can't say that we are net zero" and "we don't make a claim to being a huge employment benefit." Volition volunteered both when it would have been easy not to.
- Minor-source permitting is legally correct. Utah County is Marginal ozone nonattainment, so NNSR is 100 tpy, and the claimed figures clear both PSD and NNSR.13 The offset question under R307-421 is genuinely open rather than cleared: that rule turns on a modeled ambient concentration, not a tonnage threshold, and no modeling is in the public record.29
- Zero operational water for the ultra-low class is sourced, not asserted, to the Bloom Energy Server 6.5 and Mainspring Linear Generator 3 MW datasheets, and §9 makes the annual estimate a binding permit condition verified before approval.
- "More protective than the current code, which has no standard for this use at all" is fair. Eagle Mountain and Bluffdale host data centers under codes with no data-center standards.
The strongest fact in the proposal is one Volition never put on a slide
The city manager, answering the Mayor on 04 AUG, supplied a number the applicant did not:
"[The city manager] stated that the existing facility had been using approximately five million gallons annually despite not being fully occupied. He noted that the proposed data center's annual consumption would therefore represent a significant reduction from the property's current water use." 04 AUG Council minutes, packet p. 67
250,000 gal/yr against ~5,000,000 gal/yr is a 95% reduction in site water use, it comes from city staff rather than the applicant, and it appears in neither slide deck.4351 Two related items deserve the same credit:
- Contaminated coolant is not going to the sewer. The Volition representative, on the record: the water would be "removed into tankers, treated, and transported to an authorized waste facility rather than discharged into the local wastewater system" (p. 66). The ordinance as drafted permits sewer discharge, which is looser than what the applicant committed to, the same pattern that runs through this whole review.
- A third councilmember built the right kind of condition. If the facility ever needed hundreds of millions of gallons it would require water infrastructure the site does not have, so prohibiting infrastructure expansion makes the water cap physically self-enforcing rather than trust-dependent (p. 69). That is the best piece of reasoning by any official in the record and a template for every other condition in this ordinance.
One caveat: the ~5M gal/yr figure is a staff statement in minutes, not a metered record. Ask for the parcel's municipal water billing history, a routine GRAMA request that either confirms the best argument in the proposal or undercuts it.
18. The company
As of 20 FEB 2025, volition.eco described a residential and commercial solar, HVAC, air-filtration, battery, and microgrid installation business. No mention of data centers anywhere. The Internet Archive holds no content capture after that date. The data center identity is roughly 12–18 months old.
TABLE 30
| Prior identity | Energi / Energi Solutions, trading as Volition Solutions, Lehi, solar and HVAC. High confidence; the company's own Instagram still carries a "Clean Energi" highlight |
| Documented lifetime capital | $2.8M, one round, MAR 2022. Zero Form D filings ever |
| Employees | 1–10 (APR 2025); 7 listed on LinkedIn now. No job postings |
| Operating data centers | Zero, anywhere, under either name |
| Own website's product range | "anywhere from 1 to 50 megawatts", while /compute and /speed on the same 12 AUG 2026 deployment say "hundreds of megawatts" 11 |
| Litigation | None found in every accessible database. BBB A+, zero complaints, zero government actions |
| Board | Four members, real credentials, Realty Income SVP, Alpheus Water Fund MD, Altamont operating partner, and a fourth from a software company later acquired by Autodesk |
Ratio: $2.8M documented capital against a ~$4B claim, roughly 1:1,430. The gas lateral alone, at $14M, is five times the company's entire documented raise.51
Two claims need correcting. "500+ MW of team experience" appears in company material only as "over 500MW in new development in the works", a forward pipeline figure, not a track record; and the Novva team-overlap claim could not be located in any company material and shows no overlap with any named Novva executive, unverified and unlocated, not disproven. Pipeline claims mostly evaporate: San Jose and Austin, nothing, and "Stockman Flats" is a real place with Public Infrastructure Districts created at owner petition but no MW figure, no data center reference, and no Volition mention in the primary record.
The counter-case. Bloom Energy is named as sponsor and partner in the city record, a NYSE company with $2.45B cash that runs exactly the third-party-ownership structures this project needs. Volition's four years deploying third-party-owned generation, batteries and microgrids under PPA structures is adjacent experience for the hardest part; the data center half is what is new. Adaptive reuse removes execution risk, the build is phased, and the company volunteered enforceability and offered CUP review that staff declined.
The problem is not bad faith. It is capitalization and track record, against a permanent entitlement.
19. The tenant chain
Spanish Fork City → Volition Industries, no operating facility, $2.8M documented capital, no SPV named → Nscale (alleged), $14.6B valuation, ~$450M run rate, $51B backlog, heavily levered → undisclosed "large brand"
Nscale has no public mention of Utah, Spanish Fork, or Volition anywhere, not its site list, newsroom, investor materials, or trade press. Pre-signing NDAs are standard, so this is not evidence of fabrication. It means the city has no independent corroboration of the tenant on a project whose entire economic case depends on one, and Volition's own timeline is expressly conditional on "a complete contract" that is not documented.
Nscale's two largest anchors are Microsoft and OpenAI, the exact two the Volition representative said are "not in play." That does not identify this site's sub-tenant, and both statements can be true. The closest structural precedent is public: Ionic Digital Inc. → Nscale → Microsoft at Ward County, Texas, a 126-month triple-net lease for 234 MW, where Ionic Digital's SEC filing states "We currently have only one customer" and warns explicitly about Nscale nonperformance. Same chain shape, with the difference that Ionic is public and discloses the risk.
The "no government, no surveillance" commitment is almost certainly sincere and almost certainly unenforceable. The city has no privity with the sub-tenant's sub-tenant, GPU workload content is not externally verifiable, and no municipality has ever enforced such a restriction. Better to ask for an audit right than accept a promise.
20. Sound and heat, the two things that reach a neighbor
The nearest existing occupied home is 1,298 ft from the property boundary, due west in Oakridge Cove.5343 "The closest homes are a mile away" is not accurate. And because the amendment applies citywide, the receptor that matters is the nearest home to whichever I-1 parcel the next applicant selects.
Heat is not perceptible at a mile and unregulated at any distance; sound level is unpredictable from public information; sound character is the real exposure and the one nothing in the code addresses.
Heat
605 to 742 MW-thermal at the permitted 393.25 MW is a real quantity that disperses fast: on-site temperature rise falls from 3.0 °F at 5 m/s to about 1.1 °F at 30 mph, and at a mile it is zero.143 Volition's "+5 °F max on-site" and "under 1 °F beyond a quarter mile" are both plausible. Nobody will feel this at a mile. The gap is regulatory, not physical: §15.3.24.090 contains no thermal standard at all, no modeling requirement and no measurement, and the Planning Commission asked for one.5143
The Planning Commission asked for a heat-impact study. Where is it, and why does the ordinance still contain no thermal standard?
Sound level
1,210 modules attenuated over 1,609 m gives 15 to 40 dBA against a 30 to 40 dBA rural night ambient. That ambient floor is not quiet in practice. A rail crossing sits directly across US-6 from the nearest residential receptors and its horn sounds through the day and night, which is the loudest recurring sound most of these homes already live with.43 The 25 dB spread is what the public record supports, not either endpoint, and it covers everything from inaudible to clearly present. Treat every figure as a lower bound: inverting a "<65 dBA @ 10 ft" spec as a point source is wrong for a cabinet 29 feet long, and finite-line and ISO 3744 treatments give 84.5 and 90.6 dBA sound power against the 82.7 used.343
The cooling plant, not the fuel cells, is the likely dominant source. In every documented complaint case nationally the driver is HVAC, chillers and blowers. Volition has no diesel, which removes the loudest source outright, but cooling is what people sue over. Microsoft is currently defending a suit from residents of Sturtevant, Wisconsin over "excessive and pervasive noise" from data center HVAC.
The binding number is stricter than the criticism suggests. §6 sets 65 dBA at the property line and 55 dBA at any residential zone boundary, at all hours, against the existing I-1 limit of 80 dBA daytime.51 That is a 15 dB reduction from what the site could lawfully do today, roughly a halving of perceived loudness, around the clock. The number is good, and the enforcement is better than this report first stated. §6 binds "at any hour", expressly covers cooling equipment, adopts the Chapter 9.32 measurement procedures, and adds that "compliance with this subsection does not excuse compliance with Chapter 9.32."51 The limit is continuing and independently enforceable, not a design target. What §6 omits is only a scheduled measurement after the plant is running, so enforcement waits on a complaint.
Field observations at an operating comparable, 14 AUG 2026 UNCALIBRATED
On 14 AUG 2026, between roughly 16:00 and 18:00, the author visited the Novva Data Center in West Jordan, interviewed six people and took uncalibrated phone-based sound readings.60
Method: perimeter roads driven twice, clockwise, at a constant 18 MPH on cruise control, only the passenger window open, microphone pointed at the property. Constant speed holds the car's own noise steady, which is what makes the relative comparisons meaningful even though the absolute level is not. Readings approximate property-line distance, though the road-to-fence setback was not recorded.
What was found. Readings ran approximately 65 dB, but wind, truck traffic, construction and neighboring commercial activity were audibly louder than any data center equipment at every point. All six interviewees reported no noise issues, all six volunteered that neighboring activity is louder than the site, and all six confirmed the diesel generators have never operated, the site having had no outage.
The six were two residents living directly across the street, two employees of the neighboring construction supplier, a security guard at that business, and Novva's own guard. Five of the six have no interest in defending the site, and the two most probative are the residents, the closest available analogue to the receptor this ordinance protects.
It was taken from public roads, with no contact with the operator, so nothing could be throttled or shut down to present a quieter site. A commissioned study is far more precise and is taken with notice; this was far less precise and taken without any. The failure modes are opposite, which is why both belong in the record.
A cheap condition, if the Council wants one. §6 requires a pre-approval analysis and schedules no measurement afterward, leaving enforcement to complaint under Chapter 9.32.51 One scheduled, unannounced property-line reading after commissioning would close that, but the limit itself already binds at all hours and needs no amendment.
Novva achieves this with no acoustic barrier at all: wrought iron fence around the entire property, which provides no meaningful attenuation.60 No one can claim a barrier is doing the work, and this report's own finding that barriers could buy back 5 to 15 dB describes headroom that has not been needed.
On sound character, the field evidence cuts against this report
Asked specifically about tonality, the answer was that nothing was annoying about the quality of the sound. It simply sounded like fans running.60 Broadband fan noise is the benign case. A narrow-band whine or hum is what generates complaints, and none was reported.
That matters because tonality is one of the strongest arguments in this report, and a field observation at an operating facility does not support it. Two limits keep it from settling the question: no spectral measurement was taken, and a moving vehicle with an open window masks subtle tonality. It says nothing about night-time audibility at distance. But it is evidence, it points against the concern, and it belongs in the record even though it weakens a point made elsewhere here.
What would actually decide whether it is noticed
A decibel limit cannot capture the failure mode that generates complaints. A narrow-band tone is picked out of a quiet background far below the level at which broadband noise registers. Two measured anchors bound the propagation question. Refractive focusing tops out around +6 dB (DOE/SERI MOD-1, Kelley et al. 1985). And the distance match is nearly exact: van den Berg's 2006 Groningen measurements found a steady source audible above background at 1,500 m in 38% of night hours against 0.7% of day hours, and a receptor at one mile sits at 1,609 m.
The wind is mostly protective, and the geometry matters more than this report first stated. Five years of KSPK ASOS observations put the canyon drainage flow moving toward 308 to 314° at night.43 The nearest homes bear roughly 263° from the site, due west, which is 45 to 50° off that axis, so they are not squarely downwind after dark.5343 Homes to the north-northwest sit closer to the drainage axis than the nearest homes do, which is where night-time exposure would concentrate if it occurs at all.
At 30 mph, wind through trees, fences and eaves puts local ambient at 50 to 60 dBA, 10 to 20 dB above the facility's estimated 35 to 45.43 That is complete masking. The worst case is not the windy nights but the opposite: wind-farm acoustics has known for decades that complaints cluster where the ground is calm while the source region is windy. The condition that could make this facility audible is narrow: light drainage flow around 2 to 5 m/s under a shallow stable layer, fast enough to carry sound and benefit from refraction, too slow to mask it.
Volition's per-unit figure is verbatim from Bloom's datasheet and it disclosed that limitation to the Council itself. Publish the property-line study, and put a receptor-located limit with a low-frequency and tonality condition into the agreement, verified after construction rather than modeled before it.
21. What would have to be true, in both directions
TABLE 31
| For the optimistic reading to be right | For this to go badly |
|---|---|
| The cross-reference to §15.3.08.060 imports the CUP chapter, preserving a hearing for every future applicant | It is surplusage, and the entitlement runs with the land with no future hearing 28 |
| The development agreement gets executed with the six covenants intact, before or with the zoning | The zoning passes first and the agreement never materializes; the text amendment does not require one |
| The acoustic study is published and a receptor-located limit with a tonality condition goes into the code | §6's pre-approval analysis is the only check, and nothing verifies the built facility |
| Volition builds the full 250 MW and the tax base materializes | Volition builds a 25–50 MW phase one, consistent with its own stated 1–50 MW product range, delivering a fraction of the $40M/yr while the full entitlement stays attached to the land forever. The most likely adverse outcome 51 |
| Volition remains the owner and operator | The site is sold or assigned. A by-right amendment runs with the land; the covenants run with the developer. A successor inherits the entitlement without the promises |
| The project gets built | It never does, and the parcel carries a 500 MW industrial entitlement into whatever comes next 11 |
Note the pattern: every adverse outcome is about the ordinance, not the applicant.
Two of them already happened once, in this exact building
Fingerhut built this structure, and the record is contemporaneous press rather than inference. The Volition representative identified the site to Council as "the approximately one-million-square-foot former Fingerhut building."51
TABLE 32
| Promised | Delivered |
|---|---|
| "more than 520 employees within two years," expanding to "as many as 800 workers" | Peak workforce 250 16 |
| ~$10.4M in new wages yearly; $5.1M in property taxes within 12 years; $163.7M Utah spend by 2004 | Closure announced FEB 2001; "about 100 of its 250 employees lost jobs"; by OCT 2001 "all of the workers are now gone" |
| A $70 million facility as Fingerhut's Western hub | "the distribution center never fully opened" |
| n/a | The city had already spent $220,000 straightening Powerhouse Road, which serves this site, for truck traffic that never came at the promised scale |
Deseret News, 20 OCT 2003 carries the 520/800 employment figures and the 163 acres; 30 OCT 2001 carries the $70M, "never fully opened," and the 100-of-250 layoffs.1617 Only the $220,000 road figure appears in both; cite them separately.
Do not say "Fingerhut got incentives and there was no clawback", the only documented public money is the $220,000 road expenditure, and anything beyond it is UNVERIFIED. No clawback failure is established: the 2001 article says only that "officials are rewriting the contract with Fingerhut to make sure the city is protected when a new owner takes over," which implies a contract existed, not that recapture failed. And this is not evidence about Volition, different company, industry, and market collapse. It is evidence about the building, the road, and the city's exposure, and about how a promise of hundreds of jobs and millions in tax base at this address has resolved once before.
One conflict, now settled: the 2003 article places the former plant on 163 acres against the assessor's 69.478.17 Three independent records agree on the smaller figure, the Assessor at 69.478641, the leasing listing at 69.95, and this review's own computation of the state parcel polygon at 69.09.105543 The 163-acre figure describes something other than this parcel, most likely a larger original assemblage, and should not be used for buffer or expansion arguments.
Where the national record actually lands
The closest structural analogue is xAI "Colossus," Memphis, per NAACP v. X.AI Corp., No. 3:26-cv-00074 (N.D. Miss., filed 14 APR 2026): "Neither xAI nor CTC Property LLC applied for or received any air permits prior to constructing and beginning to operate these sixteen gas turbines" (¶197), reaching "thirty-five turbines for a total generating capacity of 421.4 MW" by 31 MAR 2025 (¶198).
Why it transfers: an off-grid, self-generating AI data center, the configuration Spanish Fork is being asked to authorize by right, where the failure was process rather than technology. Why it does not: xAI ran combustion turbines against Volition's CARB-certified fuel cells at roughly 1/70th the NOx per MWh. These are allegations in a filed complaint, not adjudicated findings. The transferable point is narrower. In Memphis, when local process failed, the correction came through the Clean Air Act citizen-suit provision because a federal statute supplied a hook. In Spanish Fork, air is DAQ's and siting is the city's, and a by-right ordinance with no post-construction verification gives the city no trigger to pull.
The Utah record cuts the other way. KSL measured ~70 dB about one block from Aligned's West Jordan campus (10 JUL 2026), residents describing constant generator blowers.26 No enforcement action, notice of violation, or citation is on the record against Aligned, and for Novva no documented complaint of any kind was found. Residents complain; nobody has been cited. Expect Volition to make that point, and it is fair.
The "broken siting promises" narrative does not survive verification
A public commenter alleged a documented national pattern of data centers breaking siting commitments. A dedicated retrieval pass across Northern Virginia, the densest data center region on earth, found no agency finding and no adjudicated violation against any named operator on any of those grounds. Every noise case traced there ends one of three ways: the county measured and found no exceedance, the conduct was legally exempt, or the facility held a valid permit.
At Vantage VA2, Sterling, the closest Virginia analogue with eight gas turbines running 24/7, county staff readings "have never exceeded 55 dBA" at the adjacent residential property.11 At AWS / Great Oak, a 1989 HVAC exemption meant "the County has no legal ability to control noise at any level from data center cooling equipment", so resident readings of 67.4 dB were real but a violation was legally impossible to find. And "Chesterton" is not a case: withdrawn JUN 2024 before any approval.
The one fully adjudicated case points somewhere else entirely. The Prince William Digital Gateway rezonings, ~2,000 acres and ~22 million sq ft, were declared void ab initio because the County Board violated Virginia's public-notice statute: a legal ad was drafted, never confirmed by the newspaper's deadline, and never ran.19
"Because the Board violated the advertising rules in Code § 15.2-2204(A)… we affirm the trial court's judgment declaring the Compass, DG South, and DG North rezonings void ab initio." Court of Appeals of Virginia, 31 MAR 2026
The project is dead, finality coming from QTS withdrawing its Supreme Court filing on 2 JUL 2026 rather than from the opinion. The largest data center approval in American history was undone by a newspaper ad that did not run.
Two conclusions follow, and they pull against each other. Both are true.
- The adversarial case against operators is weaker than the public conversation suggests. Where noise is measured by an authority with jurisdiction, exceedances mostly are not found.
- The failures that actually get remedied are failures of local process. Digital Gateway died over notice. Great Oak went unremedied for years over a definitional exemption. Vantage's turbines entered without additional review because Loudoun's zoning definition swept "associated utility infrastructure" inside the term "data center", structurally similar to what §15.3.24 does in combining data center and generation into one administratively-approved use.11
The lesson is not "watch the applicant." It is that the ordinance is the only thing that will still be here in ten years.
22. Four arguments not to make, because the evidence refutes them
An adversarial review earns its keep as much by disarming bad arguments as by finding good ones. Each of these circulates in data center opposition, and each would be corrected in the room.
1. "Data centers lower nearby property values." The verifiable literature does not support it, and the strongest study finds the opposite.62 The legitimate version of this concern is a question, not a claim: no study has measured a data center paired with a 393 MW on-site power plant. Ask which coefficient this facility fits. Do not assert the answer.
2. "$120 billion in off-balance-sheet AI financing, per the Bank for International Settlements." Misattributed. The figure is from the Financial Times, 24 DEC 2025; both relevant BIS publications return zero matches for it. BIS economists did call these structures "shadow borrowing", under the usual disclaimer that the views are the authors' own. Moody's $662 billion is the better number and is properly attributable. The concern is real; the citation is not, and attributing it to BIS invites a correction that discredits the point.
3. "The project will be abandoned and stick the city with stranded infrastructure." No documented case of a US municipality left with stranded infrastructure by a data center bankruptcy was found. Kearney, Nebraska's city manager stated Compute North's payments "are paid in full." Cyxtera's facilities were bought and kept running.
Sungard, Core Scientific, Applied Digital, and TeraWulf were never researched. The correct statement is "no such case was found," not "no such case exists."
4. "Ratepayers will subsidize this." The critique applies to grid-connected large loads whose costs get socialized. The islanded design is the answer to this criticism rather than an instance of it.
5. "The fuel cells and the compute load will expose neighbors to electromagnetic fields." The distances defeat this before the technology matters. NIEHS, reporting WHO measurements, puts a 230 kV transmission line at 57.5 mG immediately beside the conductors, 7.1 mG at 100 ft, and 1.8 mG at 200 ft, and states that beyond about 300 ft the field is indistinguishable from ordinary household background of roughly 0.5 to 4 mG.36 The nearest existing home is 1,298 ft away, and ICNIRP's public reference level for 60 Hz magnetic fields is 200 µT, or 2,000 mG.5337 For scale, the same federal booklet measures a hair dryer at 300 mG at six inches.36
And this facility has no transmission line at all. §5 requires permanent electrical isolation with no interconnection, parallel operation, or export, so the grid-tie infrastructure that produces the fields in every one of these studies is absent by design.51
The area's existing 60 Hz environment is set by transmission the facility has nothing to do with. Four 345 kV circuits, two 138 kV circuits and roughly a dozen 115 kV lines converge at the Spanish Fork substation under a mile north of the site.40 A residence across the street from any energized transmission line sits in a measurably higher power-frequency field than one 1,298 ft from a facility with no line at all.3643 State that carefully if at all. "You are already exposed to more" reads as dismissive and invites the reply "so you concede there is exposure." The affirmative version needs no comparison: there is no transmission line, and beyond 300 ft the field is household background. And note a technical point that a knowledgeable objector would raise: magnetic field scales with current, electric field with voltage, so a line's kV rating does not by itself establish its magnetic field, and a heavily loaded 115 kV circuit can exceed a lightly loaded 345 kV one.36
The professional literature on data centers and EMF runs in the opposite direction from the concern. CIGRE's 2025 review of the subject is about transmission lines interfering with data centers, not data centers emitting toward neighbors, and the design reference it cites, TIA-942-C Annex F, recommends keeping the data hall itself below 37.5 mG to protect the equipment.38 That is an immunity specification for servers, not an emission limit for residents.
Power electronics genuinely differ from rotating machines: an inverter switches at kilohertz and produces harmonics a diesel alternator does not, while a diesel set produces voltage transients on load steps that an inverter does not. IEEE 519 caps voltage total harmonic distortion at 5% at the point of common coupling, and IEC 61000-6-4 governs conducted and radiated emissions for industrial equipment.39 With no point of common coupling, none of it can propagate onto the municipal system. §15.3.24 contains no EMF or EMC standard, and no regulator supplies one for a non-interconnected facility, but unlike the missing thermal standard this gap has no receptor. Do not spend Council time on it.
And one argument the record hands the Council, fully drafted
Columbia Law School's Sabin Center for Climate Change Law recommends decommissioning bonds for data centers, and names two local ordinances operating at comparable scale: Susquehanna County and Smithfield Township, Pennsylvania. §15.3.24's decommissioning provision is the weakest in the ordinance, and Volition's documented lifetime capital is $2.8 million against a $4 billion build.1151
Require a decommissioning bond or escrow sized to actual removal cost, reviewed on a fixed cycle, running with the land rather than with the applicant. Susquehanna County and Smithfield Township, PA have adopted ordinances that do exactly this.
This is the one gap where the Council can be handed a solution instead of a problem, and it survives every optimistic assumption about Volition, because it only matters if Volition is no longer the owner.
23. Where this report is incomplete
Three national cases were run down and each is narrower than its reputation. Cheyenne is real but is not about Meta's operations: the Board of Public Utilities issued a Notice of Violation on 2 JUL 2026 naming Goat Systems LLC over Cupriavidus gilardii contamination tied to construction-phase fill-and-flush discharge, proposed a $10,000 fine, and Meta appealed on 14 JUL disputing which entity held the permit. Unresolved, and resting on regional press rather than the agency filing. Chandler and Mesa are confirmed negatives: noise complaints never escalated past voluntary mitigation, and both cities responded with prospective ordinances rather than citations. The Dalles was a public-records fight, not a water-use violation: the city sued to keep Google's water data secret, lost, and settled. No water violation was ever found against Google there. Do not cite The Dalles as an operator violation.
Unverified and must not be stated at the hearing: the public commenter's broken-promise claims beyond the Northern Virginia set, which was retrieved and largely refuted; and a second public commenter's BIS / $120B claim, traced and misattributed, the figure is Financial Times.28
Known limits on the numbers here:
- The noise model's source term is the weakest link. The independent check against KSL's measured ~70 dB at Aligned produces 63.6 dBA, evidence against the source term, not for it. Treat every noise figure here as a lower bound and the property-line study as the only authority.26
- The per-truck comparison depends on an assumed 100,000 mi/truck-year that appears in no document. On the deck's own basis, 3,500 trips/month at a 10-mile round trip, the comparison is far worse for the claim. The claim cannot be evaluated without a stated basis, which is why the fleet-level figure (2.2–2.3×) is the one to rely on.43
- No traffic count for this building exists in the public record, by the city, the applicant, or this review. Every truck figure in this report is calculated here from published ITE rates against the verified 1,054,000 sq ft, not measured and not taken from the applicant.414243 The building is mostly vacant today and its present truck volume is very low, unmeasured, and deliberately not asserted anywhere in this report: the comparison throughout is the proposed data center against the fully tenanted warehouse, not against current conditions. Two limits on the calculation: ITE rates are national averages whose observed spread at real sites is wide, PennDOT measured 0.04 to 0.38 truck trip ends per 1,000 sq ft against ITE's predicted 0.54 for buildings of this size class; and the split between LU 150 and LU 154 depends on an operating characteristic no one has specified, since the tenant is unknown.42
- The depreciation curve applies R884-24P-33, a personal property schedule. A building retrofit is real property and depreciates differently.14 The pro forma request stands; the curve is illustrative.
- The CO2 method's agreement with Bloom's own datasheet is circular, same stoichiometry, same efficiency range.25 The genuine validation is the 1% agreement with Novva's regulator-issued Utah permit, derived independently.
Potential to emit at the authorized nameplate. At the CARB DG certification standard of 0.07 lb/MWh, which is the highest rate a certified fuel cell could legally emit and 23× Bloom's published 0.003 lb/MWh, at an 85% capacity factor:330
250 MW × 8,760 h × 0.85 × 0.07 lb/MWh ÷ 2,000 = 65 tons/yr 393.25 MW × 8,760 h × 0.85 × 0.07 lb/MWh ÷ 2,000 = 103 tons/yr 500 MW × 8,760 h × 0.85 × 0.07 lb/MWh ÷ 2,000 = 130 tons/yr
for scale, at Bloom's published 0.003 lb/MWh, 500 MW gives 5.6 tons/yr
Both the permitted nameplate and the ordinance cap cross the 100 tpy NNSR major-source threshold for this Marginal ozone area.13 ⚠ But be careful with this one: it requires a unit emitting at the CARB certification ceiling, 23× worse than Bloom's published rate, so it is an argument about what the ordinance would permit a future applicant to build, not a prediction about this equipment.31143 A potential-to-emit cap in the code, the provision the Justification Statement wrongly claims exists, is the one thing that would foreclose this permanently.
Utah has no 50 tons-per-year county offset trigger, and the rule often cited for one does not contain it. R307-421 is Permits: PM10 Offset Requirements in Salt Lake County and Utah County, and its applicability test is a modeled ambient concentration, 1.0 µg/m³ annual or 3.0 µg/m³ 24-hour, not a tonnage figure.29 Whether an offset obligation attaches here is a question for R307-403 and for modeling the public record does not contain. Do not assert a 50 tpy threshold at the podium. Note separately that the nearest comparable, Novva, was required to obtain 47 tpy of NOx emission reduction credits to satisfy R307-421.31
Two things the ordinance is sometimes accused of, which it does not do: it does not permit unlimited merchant power plants (§2 requires generation "scaled to serve" on-site load, and the definition bars offsite sale), and it does not lack a receptor-located noise limit (§6 sets 55 dBA at any residential zone boundary).11
One fiscal item nobody has raised, and it runs in the city's favor: a 250 MW facility at 75% load consumes roughly 10 Bcf of natural gas per year. Utah municipalities levy a municipal energy sales and use tax on gas delivered within their boundaries.51 That is plausibly city-retained revenue comparable to Spanish Fork's entire 10.0% share of the property tax, and it appears nowhere in the fiscal case Volition presented or in this report's own analysis until now.
24. About the author
The author is a Spanish Fork resident and lives approximately one mile from the subject site. He has no financial interest in Volition Industries, in any competing applicant, or in the subject parcel, and receives no compensation from any party to this proceeding. This report was prepared independently and at no one's direction.
Sources
Every number here traces to a primary document
75 cited sources, numbered as they first appear, each linked back to the sentence that uses it. All 76 URLs were re-checked on 17 AUG 2026 and 75 return HTTP 200. One, the SSRN housing-price paper, returns 403 behind a CAPTCHA and is marked in the report as not citable. Three entries have no web address: the applicant's printed handout, the author's field observations, and the Planning Commission auto-caption transcript.
- ↩ Utah DAQ, Intent to Approve DAQE-IN163550001-26, Volition Industries Inc. Spanish Fork Data Center, signed 4 AUG 2026 by Alan D. Humpherys, New Source Review Section Manager daqpermitting.utah.gov
- ↩ Utah DAQ, public notice DAQE-NN163550001-26, published The Daily Herald 6 AUG 2026 daqpermitting.utah.gov
- ↩ Bloom Energy Server datasheet, ES 6.5, document 1016932-20260204, 4 FEB 2026 bloomenergy.com
- ↩ Volition Industries, project page for Spanish Fork, the applicant's live public page and one of the two materials distributed at its 15 AUG 2026 community meeting, the other being the printed handout at . The handout's QR code resolves here. Captured 15 AUG 2026, HTTP 200, byte-identical on re-fetch volition.eco
- ↩ Utah Municipal Power Agency, FY2022 Integrated Resource Plan, 30 NOV 2022 (Spanish Fork customer profile p. xiii; load tables pp. 81-82; resource table p. 30) wapa.gov
- ↩ Utah Geological Survey, Table 5.6, Hydroelectric Power Plants in Utah, reproducing EIA Form EIA-860, data through 2024 geology.utah.gov
- ↩ Utah Geological Survey, Table 5.7, Solar Power Plants in Utah, reproducing EIA Form EIA-860, data through 2025 geology.utah.gov
- ↩ Utah Geological Survey, Table 5.8, Biomass, Wind, and Other Power Plants in Utah, reproducing EIA Form EIA-860, data through 2024 geology.utah.gov
- ↩ Utah DAQ Air Emissions Inventory, live ArcGIS FeatureServer query filtered to Utah County, retrieved 15 AUG 2026 (256 facility-year records, 71 facilities, reporting years 2017-2025) services1.arcgis.com
- ↩ Utah County Assessor, parcel 67:228:0003 property record utahcounty.gov
- ↩ Spanish Fork City, Title 15 Land Use, archived codified text, 130 pp., last internal revision 09/2019. This document predates the amendment and does not contain it: zero occurrences of "data center," "Onsite Power Generation," "megawatt," or "55 dBA". It is cited only for provisions already codified, principally the I-1 Light Industrial zone at §15.3.16.120 and the Conditional Use Permit chapter at §15.3.08.060, whose subsection (D)(2) reads "The Commission shall hold at least one (1) public hearing on the application" and whose subsection (C) lists the five mandatory findings. The amendment text itself is in the 18 AUG Council packet, cms.spanishfork.org
- ↩ Utah S.B. 132 (2025), enrolled, creating the statutory category closed private generation system le.utah.gov
- ↩ EPA Green Book, Utah nonattainment and maintenance areas (Southern Wasatch Front, Marginal ozone) www3.epa.gov
- ↩ Utah State Tax Commission, 2026 Personal Property Valuation Schedules (Utah Admin Code R884-24P-33) files.tax.utah.gov
- ↩ Utah County Treasurer, certified property tax rates by tax area utahcounty.gov
- ↩ Deseret News, “Fingerhut to sell Sp. Fork facility,” 30 OCT 2001 deseret.com
- ↩ Deseret News, “Gigantic Spanish Fork center taking big steps,” 20 OCT 2003 deseret.com
- ↩ NBER Working Paper w35194, data centers and house-price indices nber.org
- ↩ Court of Appeals of Virginia, Prince William Digital Gateway opinion, 31 MAR 2026 vacourts.gov
- ↩ Utah Public Meeting Notice, Spanish Fork City Council agenda, 18 AUG 2026, item 7.3 utah.gov
- ↩ Spanish Fork City, Power Department, net metering and SharedSolar spanishfork.gov
- ↩ Skyline Electric, Spanish Fork Solar Farm project record (4.7 MW, ~12,000 panels, 27 acres, built on a closed landfill) skyline.us
- ↩ U.S. Bureau of Reclamation, Strawberry Valley Project history (Eric A. Stene) usbr.gov
- ↩ DataCenterDynamics, “Oracle to deploy up to 2.45GW of Bloom fuel cells,” Doña Ana County, New Mexico datacenterdynamics.com
- ↩ EPA, GHG Emission Factors Hub (natural gas 53.06 kg CO2/MMBtu, HHV) epa.gov
- ↩ KSL, measured sound levels at the Aligned data center campus, West Jordan ksl.com
- ↩ U.S. Energy Information Administration, State Electricity Emissions dataset (Utah 2024, Total Electric Power Industry, All Sources: 21,120,098 metric tons CO2; 21,168 metric tons NOx) with net generation of 35,133,906 MWh from the Utah state electricity profile eia.gov
- ↩ Utah Admin. Code R307-401-7, Public Notice (30-day comment period; hearing request within 15 days of legal notice) law.cornell.edu
- ↩ Utah Admin. Code R307-421, Permits: PM10 Offset Requirements in Salt Lake County and Utah County. The rule is a PM10 offset rule, and its applicability test is a modeled ambient concentration, not a tons-per-year threshold: R307-421-2 applies it to new or modified sources of sulfur dioxide or oxides of nitrogen located in or impacting Salt Lake or Utah County, where "the modeled impact is greater than 1.0 microgram/cubic meter for a one-year averaging period or 3.0 micrograms/cubic meter for a 24-hour averaging period." No 50 tons-per-year figure appears in the rule. R307-421-5 further provides that the rule takes effect in a county only upon EPA redesignation to PM10 attainment, with R307-403 controlling until then law.cornell.edu
- ↩ California Air Resources Board, Distributed Generation Certification Program (certification standard 0.07 lb NOx/MWh; Bloom Executive Order DG-058) ww2.arb.ca.gov
- ↩ Utah DAQ, Approval Order DAQE-AN160660003-24, Novva West Jordan, 19 DEC 2024 (72 gas reciprocating engines, 37 diesel generators, 235.6 MW, 51.28 tpy NOx, 997,261 tpy CO2e, 31.6 tpy HAPs) daqpermitting.utah.gov
- ↩ Utah DAQ, Approval Order DAQE-AN162810001-26, Joule Capital Partners, Fillmore, Millard County, 22 JAN 2026 (~175 MW, 230.12 tpy NOx, 865,632 tpy CO2e, New Major Source) daqpermitting.utah.gov
- ↩ PacifiCorp, thermal generation fleet (Lake Side Power Plant, Vineyard, Utah) pacificorp.com
- ↩ UAMPS, generation projects (Nebo Power Station, Payson, 140 MW combined cycle) uamps.com
- ↩ Mountain Country Foods, Utah operations (195 E 1600 N and 2102 N Main Street, Spanish Fork) mcfoods.com
- ↩ National Institute of Environmental Health Sciences. (2002). EMF: Electric and Magnetic Fields Associated with the Use of Electric Power, Questions & Answers. NIEHS/NIH. Transmission-line figures therein attributed to WHO (2010) niehs.nih.gov
- ↩ ICNIRP. (2010). Guidelines for Limiting Exposure to Time-Varying Electric and Magnetic Fields (1 Hz to 100 kHz). Health Physics 99(6):818-836. General-public reference level for 50/60 Hz magnetic fields, 200 microtesla icnirp.org
- ↩ CIGRE. (2025). “EMF Consideration for Data Centers Near Transmission Lines: Corridor Width Recommendations,” ELECTRA No. 341, August 2025, citing TIA-942-C Annex F and IEC 61000-4-8 electra.cigre.org
- ↩ IEEE Std 519, Recommended Practice and Requirements for Harmonic Control in Electric Power Systems (5% voltage THD at the point of common coupling); EN/IEC 61000-6-4, emission standard for industrial environments standards.ieee.org
- ↩ U.S. Department of Homeland Security, Homeland Infrastructure Foundation-Level Data (HIFLD), Electric Power Transmission Lines feature service, queried 17 AUG 2026 for the envelope around Spanish Fork (23 circuits returned; owners, kV ratings and terminal substations as attributed in the layer). Parcel centroid and bearing computed from the Utah LIR parcel polygon for 67:228:0003 services1.arcgis.com
- ↩ New Jersey Department of Transportation, ITE trip generation rates and equations as used by the NJDOT Highway Access Permit program (rates current as of 21 Apr 2023). Land Use 150 Warehousing weekday daily
1.58*(X/1000)+45.54, weekend daily(X/1000)0.15; Land Use 154 High-Cube Transload and Short-Term Storage weekday daily(X/1000)1.40, weekend daily(X/1000)*0.94nj.gov - ↩ Pennsylvania Department of Transportation. (2024, June). Warehouse Trip Generation technical memorandum, based on ITE Trip Generation Manual, 11th Edition, with observed counts at 15 warehouse sites. Table 2 (ITE LU 150 truck rate 0.54-0.64 per 1,000 sq ft), Table 4 (ITE LU 154 truck rate 0.22), Table 8 (observed truck share of daily trips, 20% for sites of at least 1,000,000 sq ft), and the ITE LU 154 high-cube definition of at least 200,000 sq ft and 24 ft ceiling height pa.gov
- ↩ Derived for this report. Computed with Utah DAQ's own method, the manufacturer's published rate times full nameplate times 8,760 hours, exactly as DAQE-IN163550001-26 builds its limits. Inputs are the Bloom ES 6.5 datasheet and the DAQ Intent to Approve; every step is shown in the calculations appendix alongside this report. The underlying datasheet bloomenergy.com
- ↩ Utah Code Title 54, Chapter 26, Large-Scale Electric Service Requirements (enacted by S.B. 318, 2025), including 54-26-504 exempting closed private generation systems from Public Service Commission oversight le.utah.gov
- ↩ Utah Code 59-12-104, sales and use tax exemptions (subsection (80), fuel cells; subsection (84), qualifying data center equipment) le.utah.gov
- ↩ Utah Code 63G-2-305, protected records (as amended by H.B. 507, 2026, subsection (2)(b)) le.utah.gov
- ↩ Utah Code 73-5-8.3, water-use disclosure before approval of a large data center (created by H.B. 76, 2026) le.utah.gov
- ↩ Utah H.B. 507 (2026), enrolled, including 11-41-202(2)(e) le.utah.gov
- ↩ Utah S.B. 282 (2026), introduced, proposed 54-26-603 annual electricity and water reporting le.utah.gov
- ↩ Utah H.B. 585 (2026), introduced, proposed data-center generation and fuel disclosure le.utah.gov
- ↩ Spanish Fork City Council agenda packet, 18 AUG 2026, 131 pp., published to the city's Diligent Community agenda portal. Cover page: "CITY COUNCIL Agenda Tuesday, August 18, 2026 at 6:00 PM." Contains the official 04 AUG 2026 Council minutes, the staff memo at p. 111, the applicant's redlined submittal at pp. 112-120, and the Exhibit A enacting text. The 500 MW cap appears at p. 114 (redlined) and p. 124 (clean text): "shall generate a minimum of 50 megawatts and not more than 500 megawatts of nameplate generating capacity, measured per Onsite Power Generation Facility." spanishfork.community.diligentoneplatform.com
- ↩ Scott Pham, Vicky Nguyen and Liz Wagner, "Bloom Energy Quietly Revises Emissions Estimates," NBC Bay Area Investigative Unit, 25 JUN 2015. Reports a 24-month Delaware average of 823 lb CO2/MWh against Bloom's then-advertised 773, and the datasheet revision to a 735-849 range that followed. Separately, on an AC Transit installation the article reports the cells held the advertised rate only for the first three of 22 months, averaging 825.31 lb CO2/MWh; that is a different system from the Delaware figure and the two should not be combined. nbcbayarea.com
- ↩ Utah AGRC Parcels_Utah_LIR statewide parcel layer, live ArcGIS FeatureServer. Used to measure boundary-to-receptor distances and, for the citywide tax base, paged in full for
PARCEL_CITY='SPANISH FORK'and deduplicated by parcel: 17,120 distinct parcels, $8,048,680,000 total real-property market value, of which 370 commercial parcels carry $1,337,300,000. services1.arcgis.com - ↩ Intermountain Health, Spanish Fork Hospital facility page (765 East Market Place Drive; opened 5 APR 2021) intermountainhealthcare.org
- ↩ Active leasing listing, Canyon Logistics Center, 4000 E US Highway 6, Spanish Fork (former Fingerhut building): 1,054,000 sq ft total, 46,944 sq ft office, up to 451,792 sq ft available divisible to 196,249, 36 dock-high doors plus one 12'x14' grade door, 36 ft clear, 45'x46' columns, ESFR, built 1998, 69.95 acres, 4,000 A / 480 V / 3-phase with ~6-8 MW additional available loopnet.com
- ↩ Utah County Assessor, individual property records queried by serial number, source of the owner-of-record names and assessed values in the taxpayer table (for example serial 270150090, Hydro Extrusion USA LLC, whose owner history also records Sapa Extrusions 2016-2018 and Cressona Aluminum 2011-2015 at the same parcel) utahcounty.gov
- ↩ Utah County, Real Property Tax Detail, the tax actually billed and paid per parcel per year. Figures above are tax year 2025, the most recent complete year; the 2026 records show $0.00 because bills have not been issued. Example: serial 26:051:0129, IHC Health Services, General Taxes $217,857.17, paid in full 02 DEC 2025 utahcounty.gov
- ↩ Utah Code 59-2-1101, exemption from property tax for property owned by a nonprofit entity and used exclusively for charitable purposes le.utah.gov
- ↩ Spanish Fork City, audited basic financial statements, fiscal year 2025, property tax revenue $5,885,340 (prior year $5,741,117), statement of activities and governmental funds spanishfork.gov
- ↩ Field observations by the author, 14 AUG 2026, Novva Data Center, West Jordan, with drive-by observation of the Utah Data Center (Bluffdale) and Meta Eagle Mountain. Six interviews. Uncalibrated phone-based sound readings taken as a controlled mobile transect: perimeter roads driven twice, clockwise, at a constant 18 MPH on cruise control, passenger window only, microphone aimed at the property, so readings are approximately property-line distance. Conditions cool, ~70 °F, windy, recent rain, approximately 16:00 to 18:00. Original observation, not a web-retrievable source. Marked
UNCALIBRATEDthroughout original observation, no web source - ↩ Volition Industries, two-sided printed handout distributed at the 15 AUG 2026 community meeting, photographed by the author. Both sides transcribed verbatim and audited at
sources/07-handout-AUG2026-transcription-and-audit.md; source images atsources/handout-AUG2026/(side A sha2569bf3c49e41b19142, side B sha256ef3d34a6fba14bda). Physical document, no web source. Its QR code resolves to original observation, no web source - ↩ Keith Waters and Terry Clower, Data Centers and 2023 Home Sales in Northern Virginia, Center for Regional Analysis, Schar School of Policy and Government, George Mason University, August 2025. Robust hedonic regression on BrightMLS 2023 sales, R² 0.8672; distance-to-data-center coefficient −$15,886 (t = 31.106, p < 0.001), distance-to-industrial +$47,523; reduced model without the industrial control retains a negative data center coefficient of −$9,745 (R² 0.864) cra.gmu.edu
- ↩ Alex Priest, Not In My Back Yard! The Effects of Data Centers on Housing Prices, SSRN 6314620, 27 FEB 2026. Difference-in-differences on Virginia air-permit issuances matched to ZIP-level house price indices; effects reported as economically small and slightly positive with confidence intervals ruling out substantial declines. Abstract verified; full text CAPTCHA-blocked on three attempts. papers.ssrn.com
- ↩ Integra Realty Resources, analysis of home values within 1.5 miles of four Indiana data centers, 2021 to 2026, based on 20 Zillow estimated values per site and presented in support of a developer's zoning variance. Per-site results as reported: Microsoft LaPorte +42% against +48% countywide; Amazon New Carlisle +49% against +32% wvpe.org
- ↩ Asa Watten, John Bistline and Geoffrey Blanford, Have Data Centers Raised Your Electric Bill? Causal Evidence from the United States, arXiv 2606.19777, 18 JUN 2026. Instrumental-variable estimate that data centers caused average US retail electricity rates to fall modestly from 2015 to 2024, with the caution that future supply constraints could reverse the effect. Two of three authors are affiliated with the Electric Power Research Institute. arxiv.org
- ↩ Utah Code 59-2-103, Rate of assessment of property, Residential property (effective 1 JUL 2025). Subsection (2): all tangible taxable property assessed and taxed at a uniform and equal rate on the basis of fair market value as valued on January 1. Subsection (3): residential property allowed a residential exemption equal to a 45% reduction in value. Subsection (5): no more than one acre of land per residential unit may qualify le.utah.gov
- ↩ Utah Code 59-2-303.1, Mandatory cyclical appraisals (effective 7 MAY 2025). Subsection (2)(a): the assessor shall annually update property values based on a systematic review of current market data, using a mass appraisal system (2)(b) jointly certified with the Commission (2)(c). Subsection (1)(a)(ii)(A): the system must be able to update all parcels each year. Subsection (3)(a): the assessor shall complete a detailed review of property characteristics for each property at least once every five years le.utah.gov
- ↩ Utah Code 59-2-704, Assessment studies, Sharing of data, Factoring assessment rates (effective 1 JAN 2026). Subsection (1)(a): the Commission annually conducts and publishes studies of the relationship between assessed value and market value in each county. Subsection (2)(a): the Commission orders each county to adjust or factor assessment rates using the most current studies. Subsection (2)(b): factoring "may include an entire county, geographical areas within a county, and separate classes of properties." le.utah.gov
- ↩ Utah Code 59-2-924, Definitions, Report of valuation of property to county auditor and commission, Transmittal by auditor to governing bodies, Calculation of certified tax rate (effective 6 MAY 2026). Subsection (1)(i): "Certified tax rate" means a tax rate that will provide the same ad valorem property tax revenue for a taxing entity as was budgeted by that taxing entity for the prior year. Subsection (4)(a): the rate is prior-year budgeted revenue divided by the adjusted aggregate taxable value computed under (4)(b), which subtracts eligible new growth at (4)(b)(iv). Subsection (1)(t)(ii)(A): "locally assessed new growth" does not include a change in value as a result of factoring in accordance with Section 59-2-704, reappraisal, or another adjustment. Subsections (1)(b)(ii)(D) and (1)(d)(ii)(A): semiconductor manufacturing equipment is excluded from both ad valorem property tax revenue and aggregate taxable value. Subsections (2) and (3): the 1 June and 13 June transmittal deadlines le.utah.gov
- ↩ Utah Code 59-2-919, Notice and public hearing requirements for certain tax increases, Exceptions, Audit (effective 6 MAY 2026). Subsection (2): a taxing entity may not levy a tax rate that exceeds its certified tax rate unless it meets the requirements of the section, which include a public statement of intent, mailed notice, newspaper advertisement, and a public hearing le.utah.gov
- ↩ Utah Code 59-2-919.1, Notice of property valuation and tax changes (effective 1 JUL 2026). Subsection (1): on or before July 22 of each year the county auditor shall notify each owner of real estate on the assessment roll. Subsection (2)(a): mailed 10 or more days before the board of equalization meets and before the taxing entity holds its hearing on a proposed increase. Subsection (2)(c): the notice must state the assessor's value, the taxable value, appeal instructions, and the appeal deadline le.utah.gov
- ↩ Utah Code 59-2-1004, Appeal to county board of equalization (subsection (3)(a): application on or before the later of September 15 or 45 days after the Section 59-2-919.1 notice) le.utah.gov
- ↩ Utah County Clerk-Auditor and Treasurer, public parcel tax and valuation records, tax years 2021 through 2025, retrieved 16 AUG 2026 for five separate owners: four in Tax Area 150 (Spanish Fork City): Hydro Extrusion USA 27:015:0090, Nature's Sunshine Products 24:046:0067, Costco Wholesale 47:308:0001, Longview Fibre / WestRock 26:049:0009. And one control in Tax Area 151 (Spanish Fork W/SPRV Drain District), Young Living Essential Oils 56:032:0001, which returns a different rate in every year and is what establishes the area rate as an area rate. Effective rate is computed as Net Taxes divided by Total Valuation for each parcel-year; the four Tax Area 150 parcels return an identical rate to six decimals in every year, which is what establishes it as an area rate rather than a parcel rate. Example record: utahcounty.gov
- ↩ Marjorie Cortez, "Utah high schools could cost $145M each in era of intense construction inflation," Deseret News, 1 DEC 2019. Reports Utah high school construction and rebuild costs including Farmington High at $77.5M (2018), Mountain Ridge High at $82M plus $5M furnishings (2019), and planned or rebuild costs of $145M for Cyprus High, $145M for Timpview High, over $119M for Hillcrest and more than $113M for Brighton. These are 2018-2019 figures and construction costs have risen since, so they are used here as a conservative floor deseret.com
- ↩ Spanish Fork City Planning Commission, public meeting of 05 AUG 2026, applicant presentation and question period, auto-captioned recording transcribed in full at
sources/05 AUG Planning Commission Meeting Transcript.md. A Volition representative, at 52:13: "I live in Provo and we intend to headquarter here in this building if we move forward with this project." Two limits travel with this citation. The recording is auto-captioned without diarization, which this report treats as a lead rather than as evidence, so nothing load-bearing rests on it alone. And the statement is conditional and forward-looking: it is an intention, not a commitment, it appears in no filed document, and Volition's published contact address remains 412 W Rivers Edge Drive, Provo. (transcript retained 16 AUG 2026) original observation, no web source